Bypass project at halfway point

The Daily Inter Lake | Hagadone News Network | UPDATED 14 years, 7 months AGO
by The Daily Inter Lake
| August 2, 2010 2:00 AM

photo

Ames Construction crews work on the south portion of the US 93 Bypass between Airport Road and US 2 Thursday afternoon. According to Montana Department of Transportation Construction Engineer Ed Toavs, the section is more than 50 percent complete.

Despite a wet spring, construction of the southern portion of the U.S. 93 Alternate Route west of Kalispell continues on schedule.

That’s the word from Montana Department of Transportation Construction Engineer Ed Toavs.

The first two parts of the project — from U.S. 93 to Airport Road and Airport Road to U.S. 2. — are more than 50 percent complete, he said.  

The third part, which consists of widening U.S. 2 where the bypass connects west of town, is less than half done.

Ames Construction of Utah is building the $13.6 million north-end portion between U.S. 2 West and Airport Road. Knife River Kalispell is building the $9 million south-end stretch from Airport Road to U.S. 93 South.

Contractors are building two roundabouts between U.S. 93 and Airport Road and a bridge that will cross Ashley Creek, Toavs said. Another roundabout is being built where the new highway crosses Foy’s Lake Road.

Due to heavy spring rains, the second part of the project has been the state’s “big challenge,” Toavs said.

The target date for completion of the southern bypass project is late October.

A separate highway project — the Hutton Ranch connector — still is dependent on land acquisition.

The Montana Department of Transportation still is negotiating with Flathead Valley Community College on acquiring land for the Hutton Ranch connector. 

Most of the design work for the connector is complete, Toavs said.

The connector road would run behind the Hutton Ranch Plaza and Mountain View Plaza shopping centers, linking Hutton Ranch Road with West Reserve Drive and bypassing the busy U.S. 93/West Reserve Drive intersection.

There is no target date for construction of the Hutton Ranch connector.

MORE IMPORTED STORIES

Traffic to flow soon on Kalispell bypass
Daily Inter-Lake | Updated 14 years, 5 months ago
Bypass to open on Nov. 17
Daily Inter-Lake | Updated 14 years, 4 months ago
Bypass section may be done this fall
Daily Inter-Lake | Updated 15 years, 1 month ago

ARTICLES BY THE DAILY INTER LAKE

April 25, 2019 10:39 p.m.

No headline

MISSOULA — Glacier Wolfpack softball had a productive day against Missoula teams, first routing Big Sky 25-0 and then edging Sentinel 4-3 on Thursday in Western AA play.

March 9, 2019 10:12 p.m.

Wolfpack falls to Capital by 20 in loser out

BUTTE — The Glacier Wolfpack (15-10) fell to Helena Capital 56-36 on Saturday, eliminating them from the Class AA state girls basketball tournament at the Butte Civic Center.

March 21, 2018 9:36 p.m.

No headline

Buffalo Hill Golf Club in Kalispell is now accepting registration forms for the upcoming men’s league season.