December Superfund Straight Talk
Coeur d'Alene Press | UPDATED 14 years, 9 months AGO
Responding to Citizen Questions about the Bunker Hill Superfund Site December, 2011
Thank you Silver Valley contractors, businesses, and community members for contributing to a successful Basin Property Remediation Program! During the summer of 2011, 240 properties were remdiated; that's about 2.8 million square feet, whichis equivalent to 58 football fields. Soil samples were gathered from 190 properties in the
Basin. Thank you for your hard work and coordination!
Q: I live in the Lower Coeur d'Alene Basin and I hear that the property remediation program is going on. What can I expect? Will my property need remediation?
A: Upper Coeur d'Alene Basin soil sampling is nearly completed and the Idaho Department of Environmental Quality (DEQ) and its contractors continue to sample properties in your area. Your property may or may not need remediation, but having an idea of what to expect as the
process proceeds will be helpful.
Homeowners' Guide to the Soil Sampling Process
1. Homeowners in the Bunker Hill Superfund Site receive Consent to Sample Forms; homeowners are asked to fill out, sign, and return the form.
2. Homeowners determine a time to meet DEQ's contractor on the property. Homeowners show the property features to the contractor so a map can be created. Features include septic, utilities, play areas, easements, wellheads, and
property pins. Homeowners retrieve a vacuum cleaner bag and
sometimes a tap water sample. This is a great time to ask
questions about the process.
3. When the map has been completed, the contractor schedules a time to take soil samples. This could be several weeks after the first visit. Homeowners can choose to arrange a time when they can be home during sampling. Homeowners can expect soil sampling to take one-tothree
days on average. Sampling holes and divots are filled after samples are taken.
4. Homeowners receive an important letter from DEQ with soil sample results, which they should keep for future title or real estate transactions. Results may come a month or more after sampling. Results may recommend remediation in specific areas or may verify that no remedial action is necessary. If remediation is recommended, homeowners will be contacted by DEQ or their contractor so a plan can be developed. Homeowners should keep a copy of the final construction plan. Homeowners would continue coordinating with the Kellogg Panhandle Health District Institutional Controls Program (ICP) to maintain records of earthwork, ceiling and attic work, and insulation removal. Thank you to the community for asking questions! Write your SST questions to Denna Grangaard at [email protected], click on "Ask Us" at
our website: www.deq.idaho.gov/bunkerhillsuperfundsite, or stop by the DEQ
Office, 1005 W. McKinley Avenue, (208) 783-5781.