Tuesday, March 18, 2025
24.0°F

Tunnel project ahead of schedule

Eric Schwartz/Daily Inter Lake | Hagadone News Network | UPDATED 13 years, 10 months AGO
by Eric Schwartz/Daily Inter Lake
| May 18, 2011 2:00 AM

photo

Crews work Tuesday on the road portion of the U.S. 93 tunnel project. Paving is expected on Thursday and the full highway may reopen this weekend.

The construction of a pedestrian tunnel beneath U.S. 93 at Flathead Valley Community College is currently about three days ahead of schedule, according to a project manager with the Montana Department of Transportation.

If the trend continues, Steve Meyers said traffic, which is currently confined to one lane in each direction through the 1,000-foot construction zone, could return to normal by the weekend.

“As far as getting the roadway opened back up to its previous configuration, I would say realistically no later than Saturday,” Meyers said. “Unless, of course, Mother Nature does something nasty.”

LHC Inc. is the general contractor for the $726,000 project that began May 9 and was expected to be completed (including bike-path approaches to the tunnel) by the end of the month.

Crews have been working 24 hours a day since Saturday and have made more progress than was initially expected on the current phase of the project.

An LHC Inc. employee said the 23 box culverts that make up the tunnel are in place and paving could begin as early as today.

Meyers said he expects paving probably will get under way Thursday instead, though that depends on the weather and the pace of construction.

“They’ve been working real hard,” Meyers said. “They’re hustling.”

After asphalt is in place, workers will need to stripe the roadway and complete bike path connections on each side of U.S. 93. Some shoulder work also will be required. The speed limit will remain reduced through the final phase of the project.

When finished, the 140-foot-long tunnel will connect the Kidsports complex and Flathead Valley Community College.

Reporter Eric Schwartz may be reached at 758-4441 or by email at eschwartz@dailyinterlake.com.

MORE IMPORTED STORIES

U.S. 93 back up to full four lanes
Daily Inter-Lake | Updated 13 years, 10 months ago
Highway traffic to be constricted
Daily Inter-Lake | Updated 13 years, 10 months ago
Major highway reconstruction project begins
Bigfork Eagle | Updated 11 years, 11 months ago

ARTICLES BY ERIC SCHWARTZ/DAILY INTER LAKE

June 10, 2011 2 a.m.

Woman pleads guilty to taking part in casino crime

The young Bigfork woman accused of helping stage a robbery at a Columbia Falls casino last year pleaded guilty to felony theft Thursday in Flathead District Court.

Tunnel project ahead of schedule
May 18, 2011 2 a.m.

Tunnel project ahead of schedule

The construction of a pedestrian tunnel beneath U.S. 93 at Flathead Valley Community College is currently about three days ahead of schedule, according to a project manager with the Montana Department of Transportation.

April 16, 2011 2 a.m.

Getaway driver gets four-year term

The man who drove a getaway vehicle — after his sister’s failed attempt at stealing an elderly woman’s purse caused the woman serious injuries — was sentenced Thursday.