Friday, December 12, 2025
39.0°F

Major alpine paving completed on Sun Road

Chris Peterson Hungry Horse News | Hagadone News Network | UPDATED 14 years, 1 month AGO
by Chris Peterson Hungry Horse News
| October 19, 2011 7:30 AM

A six-mile alpine section of the Going-to-the Sun Road in Glacier National Park neared completion this fall. Crews finished final paving of the road from Big Bend on the west side to Siyeh Bend on the east side, Park spokeswoman Denise Germann said last week.

Work continues on the west side of the highway in several locations. The last section of alpine work is from Haystack Creek to Big Bend. That work started this summer. The alpine section of the Sun Road should be entirely completed by 2013.

Since the early 1990s, the National Park Service and the Federal Highway Administration have spent $101.5 million on the highway, most of that over the past six years.

In 2005, Sen. Max Baucus secured a $50 million earmark in a federal highways bill to fix the highway. Later, the Obama administration sent $32.3 million in federal stimulus money toward the project. Stimulus money was used to reconstruct the road from Big Bend to Siyeh Bend.

Rather than entirely shut down the highway, road work has been done in phases - and plenty of phases remain to be done, including the sections between West Glacier and Logan Creek and from St. Mary to Rising Sun. The remaining projects, however, are contingent on the National Park Service securing funding in the coming years.

ARTICLES BY CHRIS PETERSON HUNGRY HORSE NEWS

April 29, 2011 2:39 p.m.

Experts forecast flooding by area rivers and streams

With continued cold weather, the potential for flooding by area rivers and streams has increased, the National Weather Service warned last week.

April 22, 2011 9:15 a.m.

Search suspended for missing skiers

The search in Grand Teton National Park for two men with ties in the Flathead has been suspended because of inclement weather. The men are believed to be lost in an avalanche.