Transit center plans advance

Brian Walker | Hagadone News Network | UPDATED 11 years, 6 months AGO
by Brian Walker
| July 23, 2013 9:00 PM

COEUR d'ALENE - Land for the first phase of a permanent public transit center in Riverstone is expected to be acquired by September and construction is pegged to start next year, a county official said.

"There's renewed enthusiasm in the project," said Christine Fueston, the county's Federal Transit Administration grant administrator.

Kootenai County commissioners today are expected to sign a memorandum of understanding with The Coeur d'Alene Tribe to cooperatively work on the project.

The site for the permanent center will be where the existing temporary center is at the southwest corner of Seltice Way and Riverstone Drive in Riverstone.

The permanent facility has been several years in the making - a conceptual plan was designed in 2009 - but has been slow to develop with a lack of funding.

However, the Tribe recently decided to not apply $1.15 million in federal stimulus funds toward a transit center in Plummer. That money will now be applied toward the Riverstone site instead.

"The (Riverstone) transit center has had a slow start, but the infusion of the money from the Tribe has gone a long way toward pushing this forward," Fueston said.

The Tribe has provided most of the money to Citylink, a free public transit system that had 32,590 rides in June.

The transit center will be built in three phases. The first will include a park-and-ride area with 160 parking spots; the second will be a transit island for buses to pull up to; the third a 6,300-square-foot building with bathrooms, a passenger seating area, a substation for law enforcement and meeting rooms.

"We haven't started the design of the building," Feuston said, adding that the structure was part of the conceptual plan.

The second and third phases of the transit center will be constructed as funding becomes available.

A total of $1.7 million has been secured for the transit center. The entire project, including land and improvments, is estimated to cost $4.6 million. However, Fueston said the cost may be lower if plans are modified.

"I'll continue to throw out a net for other funds," Feuston said.

Feuston declined to say what the estimated cost for the land for the first phase will be because an appraisal from the Federal Transit Administration isn't supposed to be complete for about two weeks.

The Tribe will own the land and the county will have the improvements completed, Fueston said.

While other sites for the transit center were discussed, Fueston said Riverstone was settled on because of its central location. It is also next to a signalized intersection, has access to Interstate 90 and the Centennial and Prairie bike trails, and the development is a live-work area.

Fueston said she hopes the entire project will be completed within three years.

MORE IMPORTED STORIES

Tribe, county buy lots for Citylink
Coeur d'Alene Press | Updated 10 years, 6 months ago
Two sites possible for NIC event center
Coeur d'Alene Press | Updated 11 years, 8 months ago
Vertical Earth makes its move
Coeur d'Alene Press | Updated 11 years, 4 months ago

ARTICLES BY BRIAN WALKER

Two arrests made in heroin trafficking case
November 27, 2018 5:56 p.m.

Two arrests made in heroin trafficking case

POST FALLS — Two Shoshone County men were arrested in a heroin trafficking case during a traffic stop on Interstate 90 at Post Falls last week.

Ingraham charged with first-degree murder
January 15, 2016 2 a.m.

Ingraham charged with first-degree murder

The 20-year-old nephew of a Post Falls man found dead in Boundary County in September has been charged with first-degree murder of his uncle.

January 20, 2013 6 a.m.

Is arming teachers a good idea or over-reaction?

No movement in region to go that route to enhance school safety

While the idea of arming teachers, as a means to increase school safety, is catching on in some areas, there’s no such momentum in Kootenai County.