Highway work wraps up west of Whitefish
The Daily Inter Lake | Hagadone News Network | UPDATED 10 years, 2 months AGO
The first half of the U.S. 93 reconstruction project west of Whitefish has been completed on schedule, general contractor Schellinger Construction said Wednesday.
Construction of the second portion of the project, which will extend to Mountainside Drive, will resume next spring
From Oct. 1 through Nov. 10, Schellinger crews worked around the clock on the $10.3 million road project.
To date, crews have installed utilities, put curbs in place, completed paving and graded sidewalks from Karrow Avenue to Fairway Drive. Golf course tunnels, pedestrian tunnels and retaining walls also were completed.
Crews are preparing for winter shutdown and plan to clear out equipment by Saturday.
“Schellinger Construction is pleased to have completed the first half of Karrow to Mountainside reconstruction both on time and with excellence for the Whitefish community,” Schellinger Project Manager Marc Blanden said in a press release. “Completing this required teamwork. The city of Whitefish and the Montana Department of Transportation have been incredibly supportive and key to completing this section before winter.”
Improvements include a wider highway, new bike paths and sidewalks, along with new storm-drain, water and sewer systems.
ARTICLES BY THE DAILY INTER LAKE
No headline
MISSOULA — Glacier Wolfpack softball had a productive day against Missoula teams, first routing Big Sky 25-0 and then edging Sentinel 4-3 on Thursday in Western AA play.
Wolfpack falls to Capital by 20 in loser out
BUTTE — The Glacier Wolfpack (15-10) fell to Helena Capital 56-36 on Saturday, eliminating them from the Class AA state girls basketball tournament at the Butte Civic Center.
No headline
Buffalo Hill Golf Club in Kalispell is now accepting registration forms for the upcoming men’s league season.