Costs going up at Priest Rapid Dam
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 11 years, 1 month AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | August 29, 2015 6:05 AM
WANAPUM DAM - Upgrading the turbines at Priest Rapids Dam will cost an additional $22,698,254. The new contract price for the entire turbine project will be $87,062,072.
Grant County PUD commissioners received an update on the project during their regular meeting on July 18 at Wanapum Dam. The commissioners awarded the initial contract for the project to Voith Hydro in July 2014.
When the contract was being prepared and awarded, PUD engineers said they hoped to refurbish and reuse some of the parts. But some of those parts will have to be replaced, said project engineer Molly Weisbeck.
The original plan was to reuse the pieces - wicket gates - that control water flow into the turbines. But Weisbeck said the PUD tested the wicket gates and discovered the material in them didn't meet the engineering standards for durability in cold weather conditions.
As a result, the contractor ran some computer models and projected the wicket gates were worn out and could break, Weisbeck said. Commissioner Larry Schaapman asked what the consequences would be if the wicket gate broke, although he was already pretty sure he knew the answer, he said.
Weisbeck said a broken wicket gate probably would damage the turbine, at a minimum. Brad Strickler, another engineer on the project, said a broken wicket gate on a Susquehanna River dam led to the damage to multiple turbines. In the worst case a broken wicket gate could contribute to flooding in the powerhouse, Strickler said.
In any scenario, it would take months to fix the broken gate and turbine, said PUD assistant manager Chuck Berrie. Depending on the damage, it could take a year or more to repair, Strickler said.
Pre-construction analysis also revealed modifications will be required to the turbine shafts, Weisbeck said. Utility district engineers also recommended modifications to the opening and closing mechanisms on the wicket gates, and installing a lighter access hatch at the bottom of the turbine shaft.
New wicket gates for all 10 turbines were projected to cost $16,725,749. The turbine shaft modifications were estimated at $5,717,189. The modifications to the wicket gate mechanisms was estimated at $158,010, and the new access hatch would cost an estimated $97,306.
Commissioner Bob Bernd said he would vote for the additional money, because the problem had to be fixed. He asked why new wicket gates weren't included in the original contract, and if the PUD's own engineers could've found the problem earlier.
Strickler said the PUD employees who wrote the project specifications were trying to reuse and refurbish as many existing parts as possible. At the time PUD employees said the costs might change after further analysis, said PUD general manager Tony Webb.
Voith Hydro had the equipment to do the computer modeling when the PUD didn't, Strickler said. The results of Voith's analysis were reviewed by outside engineers, said Stuart Hammond, part of the PUD engineering team.
Bernd asked if PUD staff had considered resubmitting the project for new bids. Strickler said they had, but adding the change to the existing contract was the most cost-effective way.
Commissioner Dale Walker asked if the new setup would increase production efficiency, but Weisbeck said it won't make any difference either way.
Weisbeck said more changes may be coming. The contractor has recommended reinforcement to some parts, making maintenance easier on others, and replacing others. She estimated the additional cost would be less than $1 million per turbine.
The turbine project is scheduled to begin in August 2016.
ARTICLES BY CHERYL SCHWEIZER
Port of Coulee City receives grant for new library, clinic upgrades
COULEE CITY — The Port of Coulee City has received a $200,000 Strategic Infrastructure Grant to start design work for a new standalone public library. Some of the money will be used for upgrades to the ambulance entrance at the Coulee City Medical Clinic, according to a port press release. The grant was awarded by the Grant County Commissioners. “The award enables the port to move forward with construction-ready plans for a new library building. The library is currently operating inside the medical clinic, which restricts clinical space and prevents the facility from functioning at full capacity,” the press release said. “Prior facility assignments have documented the need for a larger, purpose-built library to meet current and future community needs.”
Ephrata man arrested near Quincy
QUINCY — An Ephrata man was booked into the Grant County Jail Wednesday on suspicion of second-degree burglary and resisting arrest after being sought for alleged burglaries and other offenses committed in the Ephrata and Coulee Dam areas. Cody Miller, 34, was also booked for attempting to elude law enforcement and two Grant County District Court warrants, said Kyle Foreman, public information officer for the Grant County Sheriff’s Office, in a media release. “They’ve been looking for him for a bit,” Foreman said in a separate interview. Miller ran from Quincy Police Department officers Wednesday morning, Foreman said.
PUD seeking comment on 2027 rates
EPHRATA — The public comment period is open for Grant County Public Utility District customers who want to weigh in on proposed 2027 PUD rates. Comments can be made on the PUD website, www.grantpud.org, under the "workshops and meetings" tab. Utility district commissioners will hold a public hearing at 2 p.m. Nov. 10 for additional customer response. People can attend the hearing in person at the commission hearing room, 30 C St. SW, Ephrata. Access also will be available online. The proposed 2027 rates include increases for all customers. The smallest increase, 3.5%, will be paid by residential, small business, irrigation and general service customers. They're designated as "core customers."