Friday, February 13, 2026
24.0°F

2 new, 5 upgraded, substations on PUD construction schedule

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 9 years, 10 months AGO
by CHERYL SCHWEIZERStaff Writer
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | April 14, 2016 6:00 AM

EPHRATA — Grant County PUD will be building two new substations and upgrading five more by the end of 2017. Construction will cost a maximum of $23.9 million.

The PUD has adopted a new way to build and fix substations, where the whole project is designed and built by the same company to PUD specifications. Andrew Munro of the PUD said utility district officials decided to use the “design-build” system as a way to speed up the process. The PUD had been looking at a backlog extending up to five years to finish current substation projects and requests, Munro explained, and the design-build system is projected to cut the construction time to about 18 months.

Commissioner Bob Bernd asked if the upgrades to the existing substations would affect customers. Mark Milacek, a PUD engineer said substations would be shut down while work is ongoing, but electricity would be routed through other substations. There shouldn’t be any service interruptions.

Substations at Babcock and Peninsula have old equipment in them that’s being replaced, Munro said. The substation at Nelson Road will be expanded. Substations in Coulee City and at Winchester are over capacity and are being upgraded to improve their reliability. The two new substations, Quincy Plains and Cloudview, are both in the Quincy area.

The Quincy Plains substation is being built for an industrial customer, and will serve that one customer, Munro said. The Cloudview substation is being built at the request of one customer, but has room for two additional industrial customers.

Construction on the Nelson Road project begins next month and is projected to be completed in September. Construction on the Babcock substation begins in June and should be completed in October. The Peninsula substation project begins in July and is scheduled for completion in November.

Coulee City substation construction starts in August and should be completed by May 2017. The Cloud View construction is scheduled to begin in October and be completed by August 2017. Construction at the Winchester substation is scheduled for October 2016 to May 2017, and construction for Quincy Plains starts in November and should be completed by August 2017.

Commissioner Dale Walker asked the construction costs for the new substations, and who pays which portion. Munro replied most is being paid by the customer. Commissioner Larry Schaapman said the customer pays 75 percent of the construction cost for the first $850,000, and the customer pays the entire cost after that.

Walker asked about the cost structure. Reliability is important for all customers, he said, but especially for the large industrial class. He asked how the costs associated with improving reliability are allocated to customer classes.

Munro said the upgrades of the four substations and expansion at Nelson Road would be required anyway, so building them in sequence will cut the cost and shorten the timeline. Assistant general manager Kevin Nordt, who takes over as general manager in June, explained those questions about cost allocation, and whether one set of ratepayers is picking up costs that should be charged to somebody else, is better suited for the discussions on rates. Those discussions are ongoing and will continue during the summer, Nordt added.

ARTICLES BY CHERYL SCHWEIZER

Moses Lake officials working to correct audit issues
February 13, 2026 3 a.m.

Moses Lake officials working to correct audit issues

MOSES LAKE — Moses Lake city officials are working to correct errors identified by the Washington State Auditor’s Office and catch up on delayed audits. Municipal Finance Director Madeline Prentice said city officials are working to have the delayed audits for 2023 and 2024 submitted by May. “Trying to get caught up on the audits is our first priority,” Prentice said. “We have actually brought in an outside accounting firm to assist us with that.”

Wheeler roundabout construction scheduled for Feb 23
February 12, 2026 4:06 p.m.

Wheeler roundabout construction scheduled for Feb 23

MOSES LAKE — If the weather cooperates, construction will begin Feb. 23 on a roundabout at the intersection of Road L Northeast and East Wheeler Road. Moses Lake’s financial contribution to the project is about $81,000. Contributions by other stakeholders in the project was not immediately available.

Moses Lake residents asked to weigh in on financial priorities
February 11, 2026 6:03 p.m.

Moses Lake residents asked to weigh in on financial priorities

MOSES LAKE — With the Moses Lake City Council working on a financial plan that will require what council member Jeremy Davis said will be hard decisions, city officials want to hear which services residents think are the most important.