Cost of Priest Rapids Dam refurbishment may increase

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 9 years, 1 month AGO
by CHERYL SCHWEIZERStaff Writer
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | June 1, 2016 6:00 AM

EPHRATA — The primary construction contract for upgrades and refurbishment to the generators and turbines at Priest Rapids Dam may exceed $100 million by the end of the 10-year project. That’s up from the current estimate for the contract of about $95 million.

Grant County PUD engineer Jeff Niehenke updated commissioners at the last commission meeting.

In answer to a question from commissioner Dale Walker, Niehenke explained the repairs and refurbishment identified to date would push the price over $100 million for the entire project contract. Alstom Hydro is the main construction contractor.

Refurbishment of the turbines and generators begins in August. There are 10 generator-turbine units, with one scheduled for refurbishment and upgrading each year.

The turbine-generator units date back to the dam construction 50 years ago. Some parts have worn out, some have been superseded by new technology. Others are at the point where they no longer work as intended. Some parts are showing signs of stress, but “the solution (to fix them) isn’t clear” yet, due to the difficulty of getting to those parts, Niehenke said.

“With any piece of equipment that’s 50 years old, we’re going to go in there and do a lot of inspection on it, and we’re likely to find some problems.” But so far the repairs and refurbishment shouldn’t affect the timeline. Refurbishment will cost about $5 million for the parts identified so far, compared with a replacement cost of $14 million, he said.

Commissioner Larry Schaapman asked if the repairs and refurbishment found so far were included in the original budget. Niehenke said engineers budgeted for repairs they knew would be needed, and added in some contingency funds. So far all expenses are within contingency, he said.

Over the course of refurbishing an entire generator, “we have ups and downs on every component. In some areas we’re doing better than we anticipated, other areas we’re doing worse,” he commented.

Engineers are still working on solutions for problems identified so far, he said, so they won’t know the impact on the total project budget until those designs are finished.

Some of the repairs and refurbishment are proving to be challenging and not all the solutions are clear yet. Figuring out the solutions will be “a very big job, and it’s going to be a lot of design work to figure out how to do this reliably.”

Some problems were anticipated, others have been discovered during the inspections, he said, and could add to the price but should be within the budget. “We have a clear idea of what the remaining engineering needs to be.” He estimated the extra engineering cost would be about $260,000.

“In total we’re looking at over $6 million across 10 units in additional work.” But that’s within the contingency, he added.

It’s an expensive process, he said, but less expensive than buying new parts. Niehenke estimated the PUD will save about $76 million by refurbishing components rather than replacing them.

Cheryl Schweizer can be reached via email at education@columbiabasinherald.com.

MORE IMPORTED STORIES

Refurbishment costs for Priest Rapids Dam may exceed $100 million
Columbia Basin Herald | Updated 9 years ago
PUD commissioners discuss dam refurbishment
Columbia Basin Herald | Updated 8 years, 1 month ago
Work proceeding on Priest Rapids refurbishment
Columbia Basin Herald | Updated 8 years, 3 months ago

ARTICLES BY CHERYL SCHWEIZER

Hot, dry, windy conditions incoming
July 15, 2025 3 a.m.

Hot, dry, windy conditions incoming

MOSES LAKE — While the winds are forecast to die down Tuesday, hot summer temperatures – and increased fire danger – will be sticking around. Jeremy Wolf, meteorologist with the National Weather Service office in Spokane, said temperatures will increase again after Tuesday. “(Temperatures) will be rebounding back up for the middle to the end of the week,” Wolf said.

Fire near Mart Road burns about one acre
July 14, 2025 6:25 p.m.

Fire near Mart Road burns about one acre

MOSES LAKE — A fire near the shore of Moses Lake Sunday afternoon only burned about an acre, but difficult terrain kept Moses Lake Fire Department crews on the scene for a while. “We’re really lucky we were able to keep it to one acre. Access to that location is really tricky,” said Heather Kok, CARES coordinator for the MLFD.

Brush fire burns near Moses Lake Walmart
July 13, 2025 6:11 p.m.

Brush fire burns near Moses Lake Walmart

UPDATE: The fire was extinguished about 7 p.m. MOSES LAKE — Moses Lake Fire Department crews were summoned to a small fire behind the Moses Lake Walmart, 1005 North Stratford Road, at about 4:45 p.m. Sunday. As of 5:30 p.m., crews are still on the scene of the fire, estimated at one to two acres. Updates will be added as the story develops.