Wednesday, January 21, 2026
26.0°F

Cost of Priest Rapids Dam refurbishment may increase

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 9 years, 7 months AGO
by CHERYL SCHWEIZERStaff Writer
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | June 1, 2016 6:00 AM

EPHRATA — The primary construction contract for upgrades and refurbishment to the generators and turbines at Priest Rapids Dam may exceed $100 million by the end of the 10-year project. That’s up from the current estimate for the contract of about $95 million.

Grant County PUD engineer Jeff Niehenke updated commissioners at the last commission meeting.

In answer to a question from commissioner Dale Walker, Niehenke explained the repairs and refurbishment identified to date would push the price over $100 million for the entire project contract. Alstom Hydro is the main construction contractor.

Refurbishment of the turbines and generators begins in August. There are 10 generator-turbine units, with one scheduled for refurbishment and upgrading each year.

The turbine-generator units date back to the dam construction 50 years ago. Some parts have worn out, some have been superseded by new technology. Others are at the point where they no longer work as intended. Some parts are showing signs of stress, but “the solution (to fix them) isn’t clear” yet, due to the difficulty of getting to those parts, Niehenke said.

“With any piece of equipment that’s 50 years old, we’re going to go in there and do a lot of inspection on it, and we’re likely to find some problems.” But so far the repairs and refurbishment shouldn’t affect the timeline. Refurbishment will cost about $5 million for the parts identified so far, compared with a replacement cost of $14 million, he said.

Commissioner Larry Schaapman asked if the repairs and refurbishment found so far were included in the original budget. Niehenke said engineers budgeted for repairs they knew would be needed, and added in some contingency funds. So far all expenses are within contingency, he said.

Over the course of refurbishing an entire generator, “we have ups and downs on every component. In some areas we’re doing better than we anticipated, other areas we’re doing worse,” he commented.

Engineers are still working on solutions for problems identified so far, he said, so they won’t know the impact on the total project budget until those designs are finished.

Some of the repairs and refurbishment are proving to be challenging and not all the solutions are clear yet. Figuring out the solutions will be “a very big job, and it’s going to be a lot of design work to figure out how to do this reliably.”

Some problems were anticipated, others have been discovered during the inspections, he said, and could add to the price but should be within the budget. “We have a clear idea of what the remaining engineering needs to be.” He estimated the extra engineering cost would be about $260,000.

“In total we’re looking at over $6 million across 10 units in additional work.” But that’s within the contingency, he added.

It’s an expensive process, he said, but less expensive than buying new parts. Niehenke estimated the PUD will save about $76 million by refurbishing components rather than replacing them.

Cheryl Schweizer can be reached via email at [email protected].

ARTICLES BY CHERYL SCHWEIZER

Aaron Garza selected as Othello Police Chief
January 20, 2026 5:35 p.m.

Aaron Garza selected as Othello Police Chief

OTHELLO — New Othello Police Chief Aaron Garza said he likes serving his community.

Othello School District to offer four-year EP&O levy
January 20, 2026 5:23 p.m.

Othello School District to offer four-year EP&O levy

OTHELLO — Othello School District voters will decide the fate of a four-year educational programs and operations levy in a special election Feb. 10. Ballots are being mailed this week. Typically, Othello has submitted a three-year levy to voters, but Othello Superintendent Pete Perez said there are no guarantees when it comes to state funding. “I think it's certainly the unease around finances in the state of Washington for schools,” Perez said. “We were trying to look for a little more predictability and stability, and so the community group felt like four years was the appropriate amount of time for us to consider.”

New location, new look for Othello Library
January 20, 2026 3:20 a.m.

New location, new look for Othello Library

OTHELLO — The Othello Library is attracting a lot of attention in its new space. “Everybody comments on how beautiful it is, and how fresh it is, and that it looks great, and that they’re really happy,” Othello Head Librarian Georgia Reitmire said. “One of our customers came in this morning, and she said, ‘Everybody in town is talking about the new library.’ And I thought, ‘That is amazing.’” The library moved to its new location, 125 E. Hemlock St., in December. While the new and old libraries are about the same size, the new library adds meeting rooms and updated spaces students can reserve to study. “We’re way busier than we used to be. Way busier,” said Jenny Nayala, library customer service specialist.