Tuesday, July 15, 2025
52.0°F

Estimates change for Priest Rapids upgrades

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 9 years, 4 months AGO
by CHERYL SCHWEIZERStaff Writer
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | March 10, 2016 5:00 AM

EPHRATA — Grant County PUD commissioners voted to approve $1.64 million in changes to the contracts for upgrading the turbines at Priest Rapids Dam. Commissioners approved the change order at the regular commission meeting Tuesday.

Construction on the 10-year project is scheduled to begin in August, with work on one turbine-generator unit per year. In February commissioners awarded an $88.7 million contract to Voith Hydro as the construction lead.

Utility district engineers working on the project hoped to refurbish some of the parts, said engineer Molly Hill, but in some cases that might not be possible. As part of the project Voith Hydro officials conducted an analysis of the turbines, and in some cases they recommended replacing parts.

The parts were expensive enough that the PUD asked for a second opinion, and in the case of the outer head covers, the second analysis also recommended replacement, Hill said. The outer head covers, as their name implies, cover the turbines.

In answer to a question from commissioner Larry Schaapman, engineer Brad Strickland said replacing one part of the head cover means replacing it all. Because of engineering and design specifications, the first one will be more expensive, Strickland said. In addition, the first one must be completed by December to keep the project on schedule, he went on, which makes it more expensive. The cost is estimated at $1.1 million. It might be necessary to replace the head covers on all 10 generators, Hill said; the remaining nine would cost about $8 million. But whether or not replacements for the other nine will be necessary is still to be determined, she added.

If new head covers are needed on the other generators, Hill said, the engineering staff is suggesting a separate contract for the entire project.

Commissioners also approved spending $287,000 to buy parts for the moveable plates that allow water to flow through the turbines, called wicket gates. The plan is to reuse those pieces, but they have to be removed and that could damage them, Hill said, so some spare parts are necessary in the opinion of the engineers.

Other spare parts were included in the request at a cost of $405,000. The parts go into a section of the turbine called the packing box and PUD employees said keeping spare parts would make maintenance more efficient.

MORE IMPORTED STORIES

Costs going up at Priest Rapid Dam
Columbia Basin Herald | Updated 9 years, 10 months ago
Turbines to be replaced at Priest Rapids Dam
Columbia Basin Herald | Updated 11 years, 1 month ago
Refurbishment costs for Priest Rapids Dam may exceed $100 million
Columbia Basin Herald | Updated 9 years ago

ARTICLES BY CHERYL SCHWEIZER

Hot, dry, windy conditions incoming
July 15, 2025 3 a.m.

Hot, dry, windy conditions incoming

MOSES LAKE — While the winds are forecast to die down Tuesday, hot summer temperatures – and increased fire danger – will be sticking around. Jeremy Wolf, meteorologist with the National Weather Service office in Spokane, said temperatures will increase again after Tuesday. “(Temperatures) will be rebounding back up for the middle to the end of the week,” Wolf said.

Fire near Mart Road burns about one acre
July 14, 2025 6:25 p.m.

Fire near Mart Road burns about one acre

MOSES LAKE — A fire near the shore of Moses Lake Sunday afternoon only burned about an acre, but difficult terrain kept Moses Lake Fire Department crews on the scene for a while. “We’re really lucky we were able to keep it to one acre. Access to that location is really tricky,” said Heather Kok, CARES coordinator for the MLFD.

Brush fire burns near Moses Lake Walmart
July 13, 2025 6:11 p.m.

Brush fire burns near Moses Lake Walmart

UPDATE: The fire was extinguished about 7 p.m. MOSES LAKE — Moses Lake Fire Department crews were summoned to a small fire behind the Moses Lake Walmart, 1005 North Stratford Road, at about 4:45 p.m. Sunday. As of 5:30 p.m., crews are still on the scene of the fire, estimated at one to two acres. Updates will be added as the story develops.