Saturday, December 06, 2025
32.0°F

Estimates change for Priest Rapids upgrades

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 9 years, 9 months AGO
by CHERYL SCHWEIZERStaff Writer
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | March 10, 2016 5:00 AM

EPHRATA — Grant County PUD commissioners voted to approve $1.64 million in changes to the contracts for upgrading the turbines at Priest Rapids Dam. Commissioners approved the change order at the regular commission meeting Tuesday.

Construction on the 10-year project is scheduled to begin in August, with work on one turbine-generator unit per year. In February commissioners awarded an $88.7 million contract to Voith Hydro as the construction lead.

Utility district engineers working on the project hoped to refurbish some of the parts, said engineer Molly Hill, but in some cases that might not be possible. As part of the project Voith Hydro officials conducted an analysis of the turbines, and in some cases they recommended replacing parts.

The parts were expensive enough that the PUD asked for a second opinion, and in the case of the outer head covers, the second analysis also recommended replacement, Hill said. The outer head covers, as their name implies, cover the turbines.

In answer to a question from commissioner Larry Schaapman, engineer Brad Strickland said replacing one part of the head cover means replacing it all. Because of engineering and design specifications, the first one will be more expensive, Strickland said. In addition, the first one must be completed by December to keep the project on schedule, he went on, which makes it more expensive. The cost is estimated at $1.1 million. It might be necessary to replace the head covers on all 10 generators, Hill said; the remaining nine would cost about $8 million. But whether or not replacements for the other nine will be necessary is still to be determined, she added.

If new head covers are needed on the other generators, Hill said, the engineering staff is suggesting a separate contract for the entire project.

Commissioners also approved spending $287,000 to buy parts for the moveable plates that allow water to flow through the turbines, called wicket gates. The plan is to reuse those pieces, but they have to be removed and that could damage them, Hill said, so some spare parts are necessary in the opinion of the engineers.

Other spare parts were included in the request at a cost of $405,000. The parts go into a section of the turbine called the packing box and PUD employees said keeping spare parts would make maintenance more efficient.

ARTICLES BY CHERYL SCHWEIZER

Moses Lake School District, teachers union reach tentative agreement
December 6, 2025 2:02 a.m.

Moses Lake School District, teachers union reach tentative agreement

MOSES LAKE — The Moses Lake Education Association announced late Friday night that the union has reached a tentative agreement with the Moses Lake School District. Classes will resume Monday, according to a press release from the MLEA.

Priest Rapids Dam oil spill still in cleanup stage
December 4, 2025 7:13 p.m.

Priest Rapids Dam oil spill still in cleanup stage

MATTAWA — People downstream of Priest Rapids Dam are being asked to look for evidence of oil on the waters of the Columbia River following a spill of mineral oil at the dam Wednesday. Department of Ecology officials are asking boaters to stay off the river between Priest Rapids and Pasco while crews work to clean up the oil, according to a PUD press release. Absorbent booms were put in the water to collect the oil downstream of the dam and are still there, said Christine Pratt, public information officer with the Grant County PUD, in the PUD press release. The booms will stay there until the Department of Ecology allows their removal.

Royal SD voters to decide on educational programs and operations levy in February
December 4, 2025 5:33 p.m.

Royal SD voters to decide on educational programs and operations levy in February

ROYAL CITY — Royal School District voters will be asked to accept or reject a two-year educational programs and operations levy request in a special election Feb. 10. If it’s approved, it would replace the district’s existing levy approved by voters in 2024. Royal Superintendent Roger Trail said the levy rate would remain unchanged.