Monday, March 09, 2026
37.0°F

Estimates change for Priest Rapids upgrades

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 9 years, 12 months AGO
by CHERYL SCHWEIZERStaff Writer
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | March 10, 2016 5:00 AM

EPHRATA — Grant County PUD commissioners voted to approve $1.64 million in changes to the contracts for upgrading the turbines at Priest Rapids Dam. Commissioners approved the change order at the regular commission meeting Tuesday.

Construction on the 10-year project is scheduled to begin in August, with work on one turbine-generator unit per year. In February commissioners awarded an $88.7 million contract to Voith Hydro as the construction lead.

Utility district engineers working on the project hoped to refurbish some of the parts, said engineer Molly Hill, but in some cases that might not be possible. As part of the project Voith Hydro officials conducted an analysis of the turbines, and in some cases they recommended replacing parts.

The parts were expensive enough that the PUD asked for a second opinion, and in the case of the outer head covers, the second analysis also recommended replacement, Hill said. The outer head covers, as their name implies, cover the turbines.

In answer to a question from commissioner Larry Schaapman, engineer Brad Strickland said replacing one part of the head cover means replacing it all. Because of engineering and design specifications, the first one will be more expensive, Strickland said. In addition, the first one must be completed by December to keep the project on schedule, he went on, which makes it more expensive. The cost is estimated at $1.1 million. It might be necessary to replace the head covers on all 10 generators, Hill said; the remaining nine would cost about $8 million. But whether or not replacements for the other nine will be necessary is still to be determined, she added.

If new head covers are needed on the other generators, Hill said, the engineering staff is suggesting a separate contract for the entire project.

Commissioners also approved spending $287,000 to buy parts for the moveable plates that allow water to flow through the turbines, called wicket gates. The plan is to reuse those pieces, but they have to be removed and that could damage them, Hill said, so some spare parts are necessary in the opinion of the engineers.

Other spare parts were included in the request at a cost of $405,000. The parts go into a section of the turbine called the packing box and PUD employees said keeping spare parts would make maintenance more efficient.

ARTICLES BY CHERYL SCHWEIZER

New Samaritan Hospital opens its doors
March 9, 2026 3:50 a.m.

New Samaritan Hospital opens its doors

MOSES LAKE — The tarp covering the “Emergency” sign at the new Samaritan Hospital could be removed a few minutes early, but it wasn’t officially open until the sign’s lighting was turned on. The timing had to be precise. “I’ve got to wait until 6:59 (a.m.),” said Jason Wilbur of Graham Construction.

Coolidge Rd. extension to improve access to Moses Lake Community Health
March 8, 2026 8:30 a.m.

Coolidge Rd. extension to improve access to Moses Lake Community Health

MOSES LAKE — Construction is scheduled to be completed in late April on a project to extend South Coolidge Street to connect it with East Wheeler Road. The goal, said Moses Lake Community Health Center Sheila Berschauer, is to improve access MLCHC.

With fewer applicants, Grant PUD trying to fill what’s left
March 9, 2026 3 a.m.

With fewer applicants, Grant PUD trying to fill what’s left

EPHRATA — A steep increase in application fees for Grant County PUD customers has reduced the number of pending applications dramatically. Andy Wendell, vice-president of customer experience, said that was one of the goals, but there were others. “There were a number of things that we wanted to do. We wanted to become contemporary. What I mean by that is that we (want to) have application processes that are providing certainty in our queue,” Wendell said. “(We wanted to ensure) that when we dedicate engineering and planning staff to reviewing applications, we want to increase the probability that we're working on applications that are going to come to fruition as much as possible. So yes, we did achieve results that we had hoped for, which is to have applicants in the queue that are more certain (to) come to fruition.”