Thursday, October 22, 2026
45.0°F

Estimates change for Priest Rapids upgrades

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 10 years, 7 months AGO
by CHERYL SCHWEIZER & Staff Writer
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | March 10, 2016 5:00 AM

EPHRATA — Grant County PUD commissioners voted to approve $1.64 million in changes to the contracts for upgrading the turbines at Priest Rapids Dam. Commissioners approved the change order at the regular commission meeting Tuesday.

Construction on the 10-year project is scheduled to begin in August, with work on one turbine-generator unit per year. In February commissioners awarded an $88.7 million contract to Voith Hydro as the construction lead.

Utility district engineers working on the project hoped to refurbish some of the parts, said engineer Molly Hill, but in some cases that might not be possible. As part of the project Voith Hydro officials conducted an analysis of the turbines, and in some cases they recommended replacing parts.

The parts were expensive enough that the PUD asked for a second opinion, and in the case of the outer head covers, the second analysis also recommended replacement, Hill said. The outer head covers, as their name implies, cover the turbines.

In answer to a question from commissioner Larry Schaapman, engineer Brad Strickland said replacing one part of the head cover means replacing it all. Because of engineering and design specifications, the first one will be more expensive, Strickland said. In addition, the first one must be completed by December to keep the project on schedule, he went on, which makes it more expensive. The cost is estimated at $1.1 million. It might be necessary to replace the head covers on all 10 generators, Hill said; the remaining nine would cost about $8 million. But whether or not replacements for the other nine will be necessary is still to be determined, she added.

If new head covers are needed on the other generators, Hill said, the engineering staff is suggesting a separate contract for the entire project.

Commissioners also approved spending $287,000 to buy parts for the moveable plates that allow water to flow through the turbines, called wicket gates. The plan is to reuse those pieces, but they have to be removed and that could damage them, Hill said, so some spare parts are necessary in the opinion of the engineers.

Other spare parts were included in the request at a cost of $405,000. The parts go into a section of the turbine called the packing box and PUD employees said keeping spare parts would make maintenance more efficient.

ARTICLES BY CHERYL SCHWEIZER

Warden man injured in tractor-trailer collision with train
October 21, 2026 6:05 p.m.

Warden man injured in tractor-trailer collision with train

BRUCE — A Warden man was transported to an out-of-area hospital after the tractor-trailer he was driving was hit by a train near Bruce at about noon Tuesday. "The extent of the driver's injuries is not known at this time," wrote Adams County Sheriff Dale Wagner in a media release. "Preliminary information indicates the semi-truck was traveling above the speed limit and failed to obey posted requiring traffic to yield at the railroad crossing. The train was traveling at a slow speed," Wagner said. "He was moving. He wasn't stuck on the tracks," he said in an earlier interview.

Othello man arrested for Moses Lake attempted burglary
October 21, 2026 5:57 p.m.

Othello man arrested for Moses Lake attempted burglary

MOSES LAKE — An Othello man jumped into Moses Lake in an unsuccessful attempt to avoid Moses Lake Police Department officers last Friday. An MLPD media release issued Wednesday said Fernando Lira, 36, was booked into the Grant County Jail on suspicion of second-degree burglary in connection with the incident. Lira allegedly attempted to burglarize a business in the 600 block of East Broadway Friday morning. The business owner discovered him and chased him off the property, the release said.

Higher revenues, expenses projected in preliminary Moses Lake city budget
October 21, 2026 5:46 p.m.

Higher revenues, expenses projected in preliminary Moses Lake city budget

MOSES LAKE — While Moses Lake city officials have reduced expenses and revenues are projected to increase by about 7.9% in the city's preliminary budget, proposed expenditures are projected to go up by about 9.5%. Assistant City Manager James Richmond emphasized the preliminary budget presented earlier this month is not cast in stone. "The projected figures are not finalized. They are requests from departments based on projected 2027 operational costs. Largely, the figures are based on guidance from the city council during the financial sustainability plan analysis," Richmond wrote in answer to questions from the Columbia Basin Herald.