Grant PUD discusses fiber options
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 8 years, 11 months AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | April 26, 2017 3:00 AM
EPHRATA — Grant County PUD commissioners will have to decide how – or if – to continue the expansion of the PUD’s fiber network. Utility district officials laid out the options under consideration during a public meeting Tuesday that attracted a full crowd to the commission meeting room in Ephrata.
Utility district commissioners asked for a review of the system in 2016, to determine what the system actually cost, what it would cost to finish and the impact that might have on electrical rates.
The PUD started working on the fiber system in 2000, and by 2016 it had cost about $256 million, said Andrew Munro of the PUD. Some fiber was installed as part of the PUD’s own operations, and Munro was asked if that cost was included in the $256 million. Munro said the cost of what’s called the PUD backbone wasn’t included.
The $256 million does include the cost of building the existing fiber system, keeping it running and paying the financing costs, minus the revenue it has generated. The study estimated electric system customers had to pay 8 to 9 percent more in electrical rates over those 16 years to pay for the fiber system.
Currently the system covers about 70 percent of Grant County, said Doug Dawson, a consultant who worked on the study. The main question under consideration is what to do about the remaining 30 percent.
Dawson said the usage rate for PUD fiber isn’t as high as it is in other areas of the country. Part of the reason for that, in his opinion, is the PUD is prohibited from selling directly to customers – it must sell to companies that in turn sell to retail customers. Commissioners already have decided to raise rates charged to internet service providers, or ISPs, by $3 per month.
Utility district officials also have to decide what a “sustainable broadband” system looks like, Munro said. One possible definition is that the build-out has to pay for itself, plus cover the costs of financing.
Getting to the remaining 30 percent of the county is going to be expensive, Munro said. The study came up with three tentative options for commissioners and PUD customers to consider.
The first would be leave the system as it is and only add customers within the existing area. That’s the cheapest option, but it leaves open the question of fairness, Munro said. The customers who don’t have fiber helped pay for the customers that have it.
The second option would be “partnership expansion,” where the system is expanded without any help from the electric system. In that case, fiber would only go to those places where the ISPs and customers would help pay the cost.
The third option would be to continue building the system, with the goal of finishing in 10 years. In that case, depending on the number of people who use it, there would be a surcharge on electrical rates, estimated between 2.7 to 4.6 percent.
Another public meeting is scheduled at 6 p.m. Thursday at the George Community Hall. In addition, a phone survey of PUD customers is planned, and a customer survey is available online Thursday. The results of the public meetings, surveys and other information will be presented to the commissioners sometime during the summer, with a goal of June or July.
Cheryl Schweizer can be reached via email at [email protected].
ARTICLES BY CHERYL SCHWEIZER
Road closures, roundabout, mean construction season underway
EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”
Ybarra announces run for Washington Senate
QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.
Othello Community Museum to open April 25
OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.