A settlement between Sandry Construction and the city of Polson has been reached, according to city officials.
The lawsuit is in regards to a breach of contract, trespass and other items, on a water main extension for a project called Center Addition, consisting of three blocks of water and sewer main that was replaced in the area of 5th Street and 10th Avenue.
According to City Manager Mark Shrives, officials learned of the lawsuit in October 2016, and since then, he said that both sides have gone “through the legal process,” including looking at the claim itself and legal fees.
Shrives said that the approved settlement was for $8,000, negotiated down from the initial claim of $32,000.
The settlement is “not admitting any liability; it’s just an agreement to settle,” he said.
During the Dec. 4 Polson City Commission meeting, commissioners met during an executive session to discuss the settlement, then passed the decision during the public portion of the meeting.
ARTICLES BY ASHLEY FOX LAKE COUNTY LEADER
Polson nonprofit receives $1M donation
Construction will remain a constant for The Boys and Girls Club of the Flathead Reservation and Lake County for the foreseeable future, after it was announced the organization received a $1 million grant to go toward a new clubhouse.
Polson High senior dies during weekend hike
A Polson High School senior died over the weekend following injuries he sustained while hiking at Mud Lake near Polson.
Snowstorm damages wall at Polson elementary school
Officials with Polson School District started the New Year with a surprise when they learned one of their buildings is in need of repair following the recent winter storm.