Transit center opens July 31
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 8 years, 9 months AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | June 22, 2017 3:00 AM
MOSES LAKE — The grand opening of the new Grant Transit Authority transit center is scheduled for July 31, with operation beginning the next day.
The new center will be open from 10 a.m. to 2 p.m. July 31, for bus riders and transit authority patrons to come in and take a look around. It’s located at the intersection of Fifth Avenue and Division Street.
The center has been under construction since fall 2016, through a really cold, snowy winter and a windy wet spring. The building’s exterior is almost complete; workers were putting the finishing touches on the exterior Wednesday morning.
The two-story building has offices and a lobby where people can wait for the bus during bad weather. That’s in addition to a bus shelter in the bus lane, which crosses the property from Division Street to Ash Street.
The new facility will be a transfer point for passengers, replacing the current one at the Surf ‘n Slide Water Park, (The bus stop at the water park still will be open, but it won’t be a transfer point.)
The transit center will be used by other mass-transit agencies and private transportation businesses, a concept known as “multi-modal.” The site will be available to other bus lines, including People for People, and as a taxi stop.
The center bus shelter is partially completed, and some of the sidewalks have been completed. Sidewalks around the building were being poured Wednesday. Part of the parking lot has been paved.
Some new bus routes will go into effect when the bus station opens Aug. 1, said JoBeth Carlson, GTA marketing and public relations manager.
Both Fifth Street and Ash Street are two lanes, and there’s a considerable amount of traffic at some times during the day at the Fifth Street-Division Street intersection. Because it’s a busy spot, buses will enter from Fifth Street and exit onto Ash Street, Carlson said. “We’ll be going around the block,” she said.
A traffic study was required as part of the permitting process for the new transit center, said acting city engineer Richard Law. City engineering officials also reviewed the data, and determined the transit center would have a low impact on traffic. Bus traffic would be distributed throughout the day, and would not have a significant impact at peak traffic hours in the morning and evening, Law said.
Cheryl Schweizer can be reached via email at [email protected].
ARTICLES BY CHERYL SCHWEIZER
Road closures, roundabout, mean construction season underway
EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”
Ybarra announces run for Washington Senate
QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.
Othello Community Museum to open April 25
OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.