Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | June 28, 2017 4:00 AM

EPHRATA — Two spillway gates at Wanapum Dam have been taken out of use while engineers investigate possible damage that could have occurred while they were being raised and lowered.

If the Grant County PUD is lucky, the fix could cost somewhere between $100,000 and $200,000. If they’re unlucky, it’s estimated the work could cost about $1 million.

Grant County PUD general manager Kevin Nordt said the problem was discovered in one gate. That prompted an inspection of all gates, and a second gate, next to the first, was found to have the same problem.

“This is a fairly recent discovery,” he said, found when the first gate was being inspected prior to scheduled maintenance.

The opening-closing mechanisms on the two gates were running into some resistance as they worked, especially while the gates were being closed. “As the gates are closing, the arms are under tremendous stress,” Nordt said. That could cause the parts to crack.

“The situation puts the gates out of service.” But the gates can’t be out of service for very long, he said.

The repairs can be added to the scope of work on the first gate, he said. Work already had been completed on the second gate, however.

The first step, Nordt said, will be a close-up inspection of the second gate, to determine what’s happening. “It’s a tight spot in there. They’re not sure how much they can move.”

If the inspectors can determine how much, if any, cracking is going on, and if any repairs can be done in the space available, then the project would cost between $100,000 and $200,000, Nordt said. The inspection would cost about $50,000.

“If we’re not lucky, though, and we have to actually go in and disassemble, then that may be somewhere on the order of a million dollars,” Nordt said.

“We know we’ve got an issue,” said commissioner Larry Schaapman. “So why don’t we just move into rehab mode?” That would save the money spent for the inspection, he said.

“Because we won’t understand the extent,” Nordt said.

“If you tore it apart anyway, you’d understand as you were tearing it apart,” Schaapman said. Nordt said the inspection would determine tearing apart — the expensive solution — was necessary, or if work could be done without that.

Cheryl Schweizer can be reached via email at [email protected].

ARTICLES BY CHERYL SCHWEIZER

Road closures, roundabout, mean construction season underway
April 3, 2026 3 a.m.

Road closures, roundabout, mean construction season underway

EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”

Ybarra announces run for Washington Senate
April 2, 2026 1:48 p.m.

Ybarra announces run for Washington Senate

QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.

Othello Community Museum to open April 25
April 1, 2026 3:45 a.m.

Othello Community Museum to open April 25

OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.