Contract approved for Somers Ave. reconstruction
HEIDI DESCH | Hagadone News Network | UPDATED 9 years, 4 months AGO
DEPUTY EDITOR, FEATURES Heidi Desch is the Deputy Editor at the Daily Inter Lake, overseeing coverage of arts, culture, lifestyle, community, and business. Desch leads reporters in developing stories that highlight the people, traditions, and events shaping Northwest Montana, guiding content across print and digital platforms. With more than 20 years of journalism experience, including serving as managing editor of the Whitefish Pilot, Desch is a graduate of the University of Montana School of Journalism. She has received multiple Montana Newspaper Association awards, including part of the team leading the Daily Inter Lake to Best Daily Newspaper in Montana Award and the General Excellence Award in 2024 and 2025. IMPACT: Heidi’s work connects readers with stories that deepen the understanding of the community beyond daily news. | March 14, 2017 6:02 PM
Whitefish City Council March 6 approved an engineering contract for the planned reconstruction of Somers Avenue.
Council OK’d a contract with Robert, Peccia & Associates for a contract in the amount of $116,200. The project consists of reconstructing Somers Avenue from Eighth Street to Second Street.
Public Works Director Craig Workman said the work includes the first phase of the engineering and the project is expected to break ground in spring of 2018.
“This project is next on the list with resort tax funds,” he said.
Council in 2014 moved Somers Avenue up on its priority list for resort tax funded reconstruction projects. At the time, the street was second in line behind West Seventh Street, which the city reconstructed last summer.
A portion of the revenue from Whitefish’s 3 percent resort tax is used to rebuild city streets.
The plan for Somers is to reconstruct about six blocks, and does not include the Somers Avenue intersections at Eighth Street or East Second Street.
The project includes replacing the existing water main within the street and upgrading the storm drainage located at the intersection.
The project consists of reconstructing all existing roadway surfacing, but is anticipated that most of the existing sidewalk will remain, expect at intersections.
Workman said public outreach on the project will begin this spring with preliminary design taking place this summer and final design is anticipated for completion in February 2018.
ARTICLES BY HEIDI DESCH
Whitefish City Council looks at ways to trim draft budget
More than a half million dollars in cuts are being offered up as a way to reduce the city of Whitefish's proposed budget for the upcoming fiscal year.
New Flathead Valley Community College Foundation director looks to keep assisting education mission
New Flathead Valley Community College Foundation director looks to keep assisting education mission
Aptly named: Scenic Point in Glacier National Park offers spectacular views
While marking the points between the switchbacks, the view only gets better with each step, showcasing the rising peaks and brilliant blue of Two Medicine Lake in the valley below.