Work proceeding on Priest Rapids refurbishment
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 8 years, 8 months AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | March 30, 2017 3:00 AM
WANAPUM DAM — Just like remodeling a house, upgrading components of a hydroelectric project brings with it some good surprises, some bad surprises and some adjustments to the budget and time schedule. Project managers Molly Hill and Jeff Niehenke updated Grant County PUD commissioners on upgrades to the turbine-generator units at Priest Rapids Dam at the commission meeting Tuesday.
Upgrades to the first generator-turbine unit started in August 2016. The plan is to upgrade one unit each year for 10 years.
Both the turbine and generator units have been disassembled, and the various parts are undoing inspection. Some unexpected problems have turned up, and PUD employees are still trying to figure out how to solve some of them.
One piece of the generator is stuck together, despite the best efforts to pry it apart, Niehenke said. That made it impossible – at least so far – to do the planned refurbishment and inspections. “At this time we’ve decided to put the unit back into service as it is, with a plan to take it out sometime in the future.”
But “this is just a continuing, evolving story over this last month. And I can’t tell you exactly where we’re at because we’re doing more inspection, more investigation,” Niehenke said. There are some options – there’s an alternative method of getting the piece apart, but that would end up costing almost as much as buying new pieces.
Replacing the piece is under discussion; that would cost about $2.5 million over the 10 units. “We’re pushing forward to start the design process (for the piece) and that will buy us about three, four months to make a decision” on buying new parts, Niehenke said.
The good news, Niehenke said, is that a different piece might not need replacement, which would save an estimated $3 million over original estimates.
Hill said rehabilitation of the first turbine cost about $400,000 more than budgeted. There were some delays, but other parts of the project were delayed so they didn't affect the overall timeline. For the next unit, PUD engineers know that more time needs to be added to the schedule for removing the existing lead paint and repainting, and taking time to do a test fitting for certain pieces.
Cheryl Schweizer can be reached at [email protected].
ARTICLES BY CHERYL SCHWEIZER
Local legislators discuss 2026 session
MOSES LAKE — Washington 13th District legislators previewed what they see as the challenges of the upcoming 2026 session at a meeting with Moses Lake city officials and residents Tuesday. State Senator Judy Warnick, R-Moses Lake, and Representative Tom Dent, R-Moses Lake along with Rep. Alex Ybarra, R-Quincy, outlined some of their plans and ideas as well as the major business of the 2026 legislative session. Warnick said the state faces some challenges.
Dorow appointed to Othello City Council
OTHELLO — Chris Dorow has been appointed to a vacant position on the Othello City Council. Dorow was appointed by unanimous vote after candidates for the seat were interviewed at the Dec. 8 council meeting. There was no discussion. Dorow replaces Denae Valdez, who resigned from the council in November. “We had seven members of the public apply for this position,” said Othello Mayor Shawn Logan.
Grant PUD seeks rate input
EPHRATA — Grant County Public Utility District customers have until Dec. 23 to submit their comments on proposed rate hikes that would go into effect in April 2026. Comments can be submitted at Grant PUD: Commission Meetings. Customers commenting at the last PUD commission meeting of 2025 said higher rates are going to be a challenge. Commissioner Terry Pyle said the PUD is facing challenges too.