New Grant PUD line under construction

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 7 years, 3 months AGO
by CHERYL SCHWEIZER
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | October 12, 2017 3:00 AM

EPHRATA — All the electrical poles currently being installed along SR 17 between Rocky Ford and Moses Lake should in place by the end of 2017. However, the line won’t go into operation for about a year.

Grant PUD commissioners received an update on the project at the regular meeting Tuesday. The Rocky Ford line is one of two major electrical system projects currently underway, said Randy Kono, PUD electrical engineer.

Currently the poles are going up along SR 17. “A lot of big sticks being put in the ground,” Kono said.

“How much does each of those big sticks cost?” asked commissioner Larry Schaapman. Kono said the laminated wood poles are about $10,000 to $15,000 each.

The second project is a transmission line at the Quincy Plains substation. Both are designed to upgrade and expand the existing system, Kono said.

The line between the Rocky Ford and Dover substations is being installed “to meet load growth in the Moses Lake area,” Kono said. Currently five substations serve that area, one providing electricity to the other four. If that one substation breaks down, currently there’s no way to get electricity to the other four, Kono said. The new line will fix that.

Total project cost will be about $8 million, Kono said. The winning bid for the pole-setting part of the project was $2,602,334. About $2.8 million will be spent on materials, he said.

The PUD did have to pay an additional $338,133 for transmission wire to replace some that was damaged. Damaged wire is a problem, Kono said, because “they (damaged wires) cause a phenomenon called corona. Corona is bad,” he said. Corona discharges can damage nearby equipment and release gases that can be harmful to humans.

The contract specifies that the poles should be installed by Dec. 22. The line actually won’t start transmitting electricity until fall 2018. Some work is required at the Rocky Ford substation before the lines can go into service, Kono said.

The Quincy Plains project will provide electricity to substations that serve the large industrial customers along Road 11 Northwest. Total project cost is about $3 million, Kono said. The contract to build the line was $896,445.

“There was a plan to energize the Quincy Plains (line) on Saturday (Oct. 7),” Kono said. However, “there was a wind advisory issued on Saturday,” and the wind was blowing so hard the project was delayed. Utility district officials are talking with the customers who will be served by the line to determine a new service date, he said.

Cheryl Schweizer can be reached via email at education@columbiabasinherald.com.

MORE IMPORTED STORIES

New power transmission line under construction
Columbia Basin Herald | Updated 7 years, 7 months ago
SEPA RULES: RCW 197-11-970 - DETERMINATION OF NONSIGNIFICANCE
Columbia Basin Herald | Updated 13 years, 7 months ago
SEPA RULES
Columbia Basin Herald | Updated 11 years, 4 months ago

ARTICLES BY CHERYL SCHWEIZER

One infrastructure project complete, others planned for Royal City
January 30, 2025 1:05 a.m.

One infrastructure project complete, others planned for Royal City

ROYAL CITY — Cross one long, long project off the list. The last section of old water line in Royal City was replaced in 2024, wrapping up a project that Mayor Michael Christensen said took a while. “Over the years we’ve been trying to upgrade our water system, and now the entire city is upgraded,” Christensen said. “That was a long time coming and it was a bit of a task.”

2024 projects, challenges continuing into 2025 in Quincy
January 30, 2025 1 a.m.

2024 projects, challenges continuing into 2025 in Quincy

QUINCY — Accommodating growth and upgrading infrastructure were the big challenges facing the city of Quincy in 2024, and they’re the challenges going into 2025. Quincy City Administrator Pat Haley said the city’s water and wastewater treatment facilities have been, and will continue to be, at the top of the agenda. “(Evaluating) what’s required in terms of growth and upgrades. Our facilities are aged, or at capacity, and that’s probably true for those cities of our size or communities that are growing,” Haley said. “So, we’re still pretty aggressively working on those things.”

Othello Public Works set for a busy 2025
January 29, 2025 1 a.m.

Othello Public Works set for a busy 2025

OTHELLO — Some long-term projects in Othello reached completion in 2024, and there’s a whole list of new projects planned for 2025. Public Works Director Robin Adolphsen summed it up. “There’s a lot going on,” she said. Summer 2024 saw the completion of a project that was first considered in 2019, the opening of the new Iron Horse playground in Lions Park. Most of the project was paid for with grants the city received from the Washington Recreation and Conservation Office and a capital appropriation from the Washington Legislature.