Saturday, November 16, 2024
36.0°F

Puerto Rico gov seeks to cancel contract

Dánica Coto | Hagadone News Network | UPDATED 7 years AGO
by Dánica Coto
| October 29, 2017 12:42 PM

photo

In this Friday, Oct. 27, 2017 photo, Rio Abajo residents, Carlos Ocasio Borrero, left, and Luis Santiago clean up debris in Utuado as recovery efforts from Hurricane Maria continue in Puerto Rico. (David Santiago/Miami Herald via AP)

photo

FILE - In this Oct. 15, 2017, file photo, Whitefish Energy Holdings workers stand on towers to restore lines damaged by Hurricane Maria in Barceloneta, Puerto Rico. The Trump administration said Oct. 27 it had no involvement in the decision to award a $300 million contract to help restore Puerto Rico’s power grid to a tiny Montana company in Interior Secretary Ryan Zinke’s hometown. White House spokesman Raj Shah said that federal officials played no role in the selection of Whitefish Energy Holdings by the Puerto Rico Electric Power Authority.(AP Photo/Ramon Espinosa, File)

photo

In this Friday, Oct. 27, 2017 photo, good samaritans of the town of Isabela make a circle of prayer with the residents of Rio Abajo in Utuado as recovery efforts from Hurricane Maria continue in Puerto Rico. (David Santiago/Miami Herald via AP)

SAN JUAN, Puerto Rico (AP) — Puerto Rico’s governor on Sunday demanded that the board of the island’s power company cancel the $300M contract with Whitefish Energy Holdings amid increased scrutiny of the Montana company’s role in Hurricane Maria recovery efforts.

The announcement by Gov. Ricardo Rossello comes as federal legislators seek to investigate the contract awarded to the small company from Interior Secretary Ryan Zinke’s hometown.

“There cannot be any kind of distraction that alters the commitment to restore electrical power as soon as possible in Puerto Rico,” Rossello said, adding that at least $8 million has been paid to Whitefish so far.

Neither Whitefish nor power company officials immediately returned messages for comment.

Rossello said he has requested that power crews from New York and Florida come help restore power in Puerto Rico and he criticized the U.S. Army Corps of Engineers for not meeting its goals. The agency could not be immediately reached for comment.

Roughly 70 percent of the island remains without power more than a month after Hurricane Maria struck the U.S. territory on Sept. 20 as a Category 4 storm with winds of up to 154 mph (245 kph). Power company Director Ricardo Ramos has said that Puerto Rico’s Electric Power Authority reached a deal with Whitefish just days before the hurricane struck. He also said that the Federal Emergency Management Agency had approved of the deal, something the agency has denied.

FEMA said this week that it has not approved any reimbursement requests from the power company for money to cover repairs to the island’s electrical system. The contract said the utility would not pay costs unallowable under FEMA grants, but it also said, “The federal government is not a party to this contract.”

FEMA has raised concerns about how Whitefish got the deal and whether the contracted prices were reasonable. The 2-year-old company had just two full-time employees when the storm hit, but it has since hired more than 300 workers.

A Whitefish contract obtained by The Associated Press found that the deal included $20,277 an hour for a heavy lift Chinook helicopter, $650 an hour for a large crane truck, $322 an hour for a foreman of a power line crew, $319 an hour for a journeyman lineman and $286 an hour for a mechanic. Each worker also gets a daily allowance of $80 for food, $332 for a hotel room and $1,000 for each flight to or from the mainland.

ARTICLES BY