Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | September 28, 2017 3:00 AM
OTHELLO — Stalled construction at the tennis courts was the subject of discussion at the Monday meeting of the Othello School Board.
In July the board approved a $498,000 contract for six new courts plus bases where lights can be installed. The contract requires the project to be completed by Nov. 30.
“I don’t drive by there every day, but I’ve probably driven by 10 times since it (the project) started, and one time there were any humans beings actually on site,” said board member Rob Simmons. When there are so few visible signs of activity, “it makes me concerned the contractor is not making it a priority,” he said.
Brian Bodah, the district’s new executive director of business services, said he had asked the architect in charge of the project about the slow progress. The architect replied that the anchor bolts for the light bases were a specialty part and couldn’t be found locally. The shipping process was disrupted by Hurricane Harvey, and the materials were stuck in Houston. No more work could be done until the light pole bases were in place.
Court paving is set for Oct. 4, and the surfacing is scheduled for Oct. 20. The architect said the subcontractor surfacing the courts “will have a plan in place should weather and temperature become an issue.” Project completion is projected for Nov. 2.
Bodah said he asked if the delay will affect the 2018 tennis season. “The answer was no.”
Simmons objected the contractor couldn’t guarantee weather wouldn’t delay the project. He was most concerned that the project doesn’t impact the 2018 tennis season, he said.
In other business, technology director Rodrigo Ozuna detailed the first steps of a project to “provide internet access to all students, basically any time, anywhere.”
The district is in the process of providing laptop computers to all students; Othello High School senior Kaiden Quigley, a student representative to the board, said computers have been distributed to OHS students within the last two weeks. Ozuna said the goal is to ensure Othello students can get access to the internet after school is out.
Research into the options is continuing, Ozuna said, but district officials are recommending installing solar panels on the district’s bus fleet as a first step. That would allow students wireless access while they’re on the bus, and the buses might be used as mobile hot spots. The second phase would be to apply for a program offered by a phone company to help provide access to homes without it.
Cheryl Schweizer can be reached via email at [email protected].
ARTICLES BY CHERYL SCHWEIZER
Road closures, roundabout, mean construction season underway
EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”
Ybarra announces run for Washington Senate
QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.
Othello Community Museum to open April 25
OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.