New wind farm to be built near Lind
Rachal Pinkerton Staff Writer | Hagadone News Network | UPDATED 6 years, 9 months AGO
LIND — Avista announced in a press release on Tuesday, March 19, that it will be purchasing power from a new wind farm to be built between Lind and Washtucna. The wind farm will be built by the Clearway Energy Group, headquartered in San Francisco, California.
The wind farm project will consist of 90 windmills. It will connect to the Avista power grid through a series of new power lines and a substation that has yet to be built.
Phase one will build approximately 60 towers and will increase local tax revenues by approximately $700,000 a year and $14 million over the life of the project. The first phase is expected to be up and running in 2020.
The announcement has caused great excitement for Adams County Commissioners and the Adams County Development Council.
“I can’t tell you how thrilled I am,” said John Marshall, chairman of the board for the Adams County Commissioners. “Last year, Avista completed the solar farm. To have them reinvest in Adams County, I am really, really pleased to have it happen so soon.”
The wind farm project has been 15 years in the making.
“Fifteen years ago, Adams County saw an opportunity that wind may come here,” said Stephen McFadden, Adams County Economic Development Director. “The county invested in towers to measure wind in the area of the towers. Nothing came of it. That original data contributed to the developer deciding to proceed with the project.”
“At the time, it hadn’t been economical to go ahead and invest and build that in Adams County,” said Marshall. “Now that customers want to have renewable energy, they have a desire to help the environment and to be more acceptable to their customers.”
The wind farm is expected to create eight to 12 full-time, permanent jobs and approximately 250 temporary construction jobs. Around 30 percent of the construction jobs are expected to be hired locally.
“We have the potential for new families to move into Adams County,” said McFadden. “Anytime we can create new jobs, get new kids in school or new people in grocery stores, it’s a win.”
Total construction time is expected to be 12 to 18 months and cost around $250 million. Clearway still has local regulatory permits and processes to get completed before construction begins.
ARTICLES BY RACHAL PINKERTON STAFF WRITER
Wahluke Junior High Robotics team to compete at state
MATTAWA – One Wahluke Junior High robotics team has secured a spot in the state robotics tournament. Coach Eduardo Martinez thinks that three of his other teams will also make it to state.
PDC receives second complaint against Othello School District
OTHELLO — Another complaint against the Othello School District was filed with the Public Disclosure Commission (PDC). The alleged violation is for the misuse of public facilities to support an election campaign.
Othello looking for donations for annual Christmas baskets
OTHELLO — About 45 years ago, four volunteer firefighters decided to make Christmas food and gift baskets and give them to seven families who needed some extra help. The next year, they gave baskets to more families. In the years since, the Othello Community Christmas Baskets has become a city-wide event with various groups raising money, food, warm clothes and toys for Othello families in need.