CFAC cleanup plan expected this spring; lawsuit delayed
CHRIS PETERSON | Hagadone News Network | UPDATED 5 years, 8 months AGO
Chris Peterson is the editor of the Hungry Horse News. He covers Columbia Falls, the Canyon, Glacier National Park and the Bob Marshall Wilderness. All told, about 4 million acres of the best parts of the planet. He can be reached at [email protected] or 406-892-2151. | December 8, 2020 11:15 PM
The wheels are still turning on the Columbia Falls Aluminum Co. Superfund site cleanup. Crews from Sandry Construction should be wrapping up removing contaminated sediments from settling ponds adjacent to the Flathead River in the coming days.
The contaminant of concern is barium, said project manager Ken Champagne of the Environmental Protection Agency.
The sediments, at least for now, are being stored on the main CFAC site under an agreement with the EPA.
Meanwhile, a draft feasibility study was completed by the company in October and is currently being reviewed by the EPA and the state Department of Environmental Quality.
The final feasibility study should be completed this spring and available for public comment. The feasibility study determines best alternatives for cleaning up the site.
On the legal front, a bench trial in federal court was supposed to start last week in front of District Court Judge Donald Molloy, but Molloy in a recent ruling said he regrettably was postponing it until June due to coronavirus concerns.
CFAC is suing former plant owner, the Atlantic Richfield o., which is owned by British Petroleum. It claims Arco created most of the pollution at the site, and as such, should be responsible for cleaning it up.
The pond cleanup, which was paid for by CFAC, went well, Champagne noted.
The south ponds were originally built in the 1960s by installing a dam and infrastructure to close off a northern side channel of the Flathead River. The south ponds were used as percolation ponds throughout the operational history of the site and now receive site storm water.
Those stormwater pipes will be removed, as will the coffer dam. The dam removal is slated for next spring, Champagne said.
Champagne takes over as project manager for the EPA as Mike Cirian is retiring.
Actual cleanup of the site is still a few years out — a best case scenario puts that possibly in 2023, assuming both litigation and design go well.
The main focus of concern has been high levels of cyanide and fluoride in groundwater below old landfills on site, where spent potliner and wastewater was dumped or years.
ARTICLES BY CHRIS PETERSON
Resort tax collection in Columbia Falls slightly less than last year
Columbia Falls' resort tax revenue came in a little less than last year, city manager Eric Hanks noted in a recent report to the city council.
Hungry Horse News at 80: A sea of change in the past 28 years, more ahead
“We’re moving to Montana,” I told my wife one day in late March, 1998.
Hungry Horse News at 80: Mel Ruder, the man who started it all
When Mel Ruder founded the Hungry Horse News in 1946, his plan was to start a newspaper in Columbia Falls (which had none at the time) and then sell it five years later.