Grant PUD sets 2020 schedule for fiber-optic lines
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 6 years, 3 months AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | January 2, 2020 11:08 PM
High-speed internet to expand near Moses Lake, Ephrata, Quincy, Electric City
EPHRATA — Fiber-optic lines will be coming to areas around Moses Lake, Ephrata, Quincy and Electric City in 2020. The tentative schedule for Grant PUD’s 2020 fiber buildout has been posted on the Grant County PUD website.
Fiber-optic cable is used for high-speed internet, which is important to businesses that need connectivity and Grant County residents who want to connect to the internet, including from remote locations.
Some of Grant PUD’s fiber-optic projects that were started in 2019 are scheduled for completion in 2020. The Ancient Lake-White Trail Road area near Quincy should be completed next week. The area along McConihe, Neppel and Stonecrest roads north of Moses Lake should be done by mid-January. The buildout along Kittleson Road, Road N Industrial and Wheeler Road is scheduled for completion in mid-February. In each case, construction was delayed because materials were delayed.
Two separate projects, one around Coulee City, the other in the Blue Lake-Alkali Lake area, were scheduled for construction in 2019, but they were delayed due to the need for additional permits. No completion date has been announced for either project.
The first project scheduled for 2020 is southeast from the Ephrata city limits, toward Rocky Ford, and southwest toward the Naylor townsite. The second project is south of Electric City along state Route 155 from Steamboat Rock to Osborn Bay on Banks Lake.
Next in priority is the area from Cave B winery, southwest of Quincy, to Beverly Burke Road, then along Road 2 Northwest/Southwest. The fourth project is south of Ephrata in the area of the South Ephrata substation.
Two additional projects are scheduled for completion in 2020, including the area between SR-283 and Road 9 Northwest near Quincy, and the area around the Gloyd townsite on Stratford Road north of Moses Lake. Construction is scheduled to begin in the Perch Point-McDonald area south of Moses Lake to Interstate 90, although that project might not be completed in 2020.
The fiber buildout began in about 2001, and about 75 percent of the county’s residents currently have access to the PUD’s fiber network. Providing fiber to the remaining 25 percent has been a subject of discussion among PUD commissioners and administrators for years.
Fiber-optic lines allow schools to access a wide variety of educational resources without leaving school. Utility district commissioners made it a priority early in the project to provide fiber to all public schools to ensure Grant County schools would remain competitive in the global economy.
Utility district commissioners decided in November 2018 to add more money to the fiber project with the goal of finishing it in five years. That timetable may be subject to some changes, depending on the availability of materials and the speed with which crews can do the work. Commissioners voted to allocate an estimated $12.5 million for the project each year between 2020 and 2023.
Cheryl Schweizer can be reached via email at [email protected].
ARTICLES BY CHERYL SCHWEIZER
Road closures, roundabout, mean construction season underway
EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”
Ybarra announces run for Washington Senate
QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.
Othello Community Museum to open April 25
OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.