Port of Moses Lake project clears hurdle

CHARLES H. FEATHERSTONE | Hagadone News Network | UPDATED 4 years, 6 months AGO
by CHARLES H. FEATHERSTONE
Staff Writer | June 30, 2020 12:03 AM

MOSES LAKE — The Federal Railroad Administration has finally approved an updated route for the long-delayed Northern Columbia Basin Railroad’s extension into the Port of Moses Lake.

“The Port of Moses Lake is relieved to finally receive federal approval to go forward with this project,” said Port Commission President Stroud Kunkle.

In 2015, the port received initial approval for the $31 million project to build several miles of new rail line from Wheeler west to the current NCBR line near the intersection of Stratford Road and Kinder Road, as well as refurbish the existing rail line going into the port.

Receipt of the money — $21 million in state and $10 million in federal grants — was held up for several years pending environmental review of the proposed changes to the route along and across Wheeler Road.

The line would replace the current NCBR rails that snake along the shores of Moses Lake near the city’s downtown.

The rail extension is intended to improve the ability of major industries to haul products in and out by rail, as well as possibly attract new businesses to the port.

“I’m excited to see this major milestone achieved,” said Sen. Judy Warnick, R-Moses Lake, a longtime supporter of the rail extension. “This project will allow the city of Moses Lake to evaluate options for lands along the waterfront and bring new products and manufacturing opportunities to the Port of Moses Lake.”

Moses Lake City Manager Allison Williams said that while the city is eyeing a “future rails to trails” for at least part of the rail line, it is “too early to talk much” about the fate of the existing rail spur.

However, before the port can lay rails, it still needs to appraise and acquire land along the proposed Wheeler corridor, according to port Executive Director Don Kersey.

“The port, and its partners, still have much work ahead,” Kersey said.

According to Milton Miller, the port’s facilities director, the port hopes to begin construction on the new rail line in fall 2021.

Charles H. Featherstone can be reached at cfeatherstone@columbiabasinherald.com.

MORE FRONT-PAGE-SLIDER STORIES

Feds release funds for port rail project
Columbia Basin Herald | Updated 4 years, 5 months ago
Port of Moses Lake buys land using eminent domain
Columbia Basin Herald | Updated 2 years, 8 months ago
Port receives nearly $1M WSDOT grant for rail project
Columbia Basin Herald | Updated 8 years, 9 months ago

ARTICLES BY CHARLES H. FEATHERSTONE

Potato prices up, sales down for first quarter 2023
July 9, 2023 1 a.m.

Potato prices up, sales down for first quarter 2023

DENVER — The value of grocery store potato sales rose 16% during the first three months of 2023 as the total volume of sales fell by 4.4%, according to a press release from PotatoesUSA, the national marketing board representing U.S. potato growers. The dollar value of all categories of U.S. potato products for the first quarter of 2023 was $4.2 billion, up from $3.6 billion for the first three months of 2022. However, the total volume of potato sales fell to 1.77 billion pounds in the first quarter of 2023 compared with 1.85 billion pounds during the same period of 2022, the press release noted. However, total grocery store potato sales for the first quarter of 2023 are still above the 1.74 billion pounds sold during the first three months of 2019 – a year before the outbreak of the COVID-19 pandemic, the press release said.

WSU Lind Dryland Research Station welcomes new director
June 30, 2023 1 a.m.

WSU Lind Dryland Research Station welcomes new director

LIND — Washington State University soil scientist and wheat breeder Mike Pumphrey was a bit dejected as he stood in front of some thin test squares of stunted, somewhat scraggly spring wheat at the university’s Lind Dryland Research Station. “As you can see, the spring wheat is having a pretty tough go of it this year,” he said. “It’s a little discouraging to stand in front of plots that are going to yield maybe about seven bushels per acre. Or something like that.” Barely two inches of rain have fallen at the station since the beginning of March, according to station records. Pumphrey, speaking to a crowd of wheat farmers, researchers, seed company representatives and students during the Lind Dryland Research Station’s annual field day on Thursday, June 15, said years like 2023 are a reminder that dryland farming is a gamble.

Wilson Creek hosts bluegrass gathering
June 23, 2023 1:30 a.m.

Wilson Creek hosts bluegrass gathering

WILSON CREEK — Bluegrass in the Park is set to start today at Wilson Creek City Park. The inaugural event is set to bring music and visitors to one of Grant County’s smallest towns. “I've been listening to bluegrass my whole life,” said the event’s organizer Shirley Billings, whose family band plays on their porch every year for the crowd at the Little Big Show. “My whole family plays bluegrass. And I just wanted to kind of get something for the community going. So I just invited all the people that I know and they’ll come and camp and jam.” ...