Construction continues on Stratford Road through late November
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 5 years, 5 months AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | October 22, 2020 1:00 AM
By CHERYL SCHWEIZER
Staff Writer
MOSES LAKE — The overnight closures of Stratford Road are about over, and the current construction project is slated for completion by late November.
Stratford is a major north-south route in Moses Lake and commercial corridor. The nightly closures of the road will end Friday.
“There may be a couple of nights of work, but the consistent nightly closures are finished,” said Lynne Lynch, communications and marketing specialist for the city of Moses Lake.
Paving should be complete by the first week in November, Lynch said.
Joe Kiyohara, project manager, said the project deadline had been extended through Nov. 24. “Unforeseen conditions have added working days,” Kiyohara said.
Most of the road surface has been replaced from the Stratford-Broadway intersection to the end of the project, about 80 feet past the intersection of Stratford and Mart roads. But there’s still a lot of digging going on: Crews are working on upgrades to the traffic lights, and replacing them where necessary.
On Wednesday, construction crews were working on replacing the traffic light at Stratford and Valley roads. The sidewalk was demolished on both sides of the road to give workers room.
Crews were digging trenches to accommodate tunneling equipment, which eliminates the need to dig a trench across the entire intersection. Jacob Villanueva ran the modest-looking piece of equipment that does the actual tunneling.
Villanueva used a pair of joysticks to maneuver the drill bit, guided by a video camera. “It’s a blast. I get to play with toys and dirt all day,” he said.
Conduit is pulled back through the tunnels for electrical wiring, as well as for fiber optic, water and gas lines.
The paving and traffic light replacement is the second half of a two-year project to upgrade Stratford Road. Water mains were replaced along the length of the road in 2019.
Moses Lake city engineer Richard Law said in an earlier interview that the Stratford-Valley intersection is being widened to accommodate a second left-turn-only lane and a second northbound through lane. The additional through lane will go all the way to the end of the project.
Curbs and the stormwater system have been upgraded, and sidewalks on the east side from Valley Road to the end of the project are being moved to accommodate the extra traffic lane.
The estimated total project cost is about $1.7 million. C&R Tractor, of Kelso, is the contractor.
Cheryl Schweizer can be reached via email at [email protected].
ARTICLES BY CHERYL SCHWEIZER
Road closures, roundabout, mean construction season underway
EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”
Ybarra announces run for Washington Senate
QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.
Othello Community Museum to open April 25
OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.