White Trail Road roundabout on tap: Traffic circle construction will affect major route in region
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 4 years, 10 months AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | January 4, 2022 1:07 AM
QUINCY — Construction is scheduled to begin in late summer or early fall 2022 on a new one-lane roundabout at White Trail Road/Road U Northwest and state Route 28, about four miles west of Quincy.
James Reynolds, engineer with the North Central Region of the Washington State Department of Transportation, said White Trail Road would be closed except for local traffic throughout most of the project.
The roundabout will be one lane in each direction. While it’s still in the design phase, he said the finished project probably will resemble the roundabout on West Bench Road and state Route 24 about a mile south of Othello.
“As far as roundabouts, it’s pretty typical of what you might see in this region,” Reynolds said.
The total project cost will be about $2.5 million, he said. Construction will take about 40 to 50 days, about two and a half months.
The project should be advertised for bid in the spring, he said, with construction tentatively scheduled to begin by August or September. But the availability of materials may affect the timeline, he said, and it could be postponed to spring 2023 if construction is delayed too long.
State Route 28 is the major route to and from Wenatchee, and an option to access Interstate 90 from the north. State Route 28 goes through Quincy, and White Trail Road has become a popular route to bypass the town.
Options to detour around the construction zone are limited.
“There are no good detours,” Reynolds said.
As a result, the construction zone will probably be a single lane of traffic, controlled by flaggers 24 hours a day. Access to White Trail Road will be restricted.
“For a good portion of the project, White Trail Road is going to be closed off,” he said. “People will have to go through Quincy to get to I-90.”
The project’s goal is reducing the possibility of serious injury and fatal collisions at the intersection, and Reynolds said the roundabout should do that.
“We see reductions of up to 80% of severe and fatal collisions (at roundabouts),” he said. “Extreme benefits for safety.”
Drivers must slow down at a roundabout, and the road is curved, and drivers don’t run into each other at right angles, Reynolds said.
ARTICLES BY CHERYL SCHWEIZER
North Cascades Highway closed, possibly for the winter
WINTHROP — Snow slides along the North Cascades Highway closed the road early Thanksgiving evening, but Washington Department of Transportation officials aren't sure yet whether the road will be closed for the winter.
Water, sewer, parks improvements in Othello capital projects plan
OTHELLO — Upgrades to the heating-cooling system at Othello City Hall, a new shelter in Lions Park and upgrades to sections of 14th Avenue are among the possible projects for 2027 included in the city's six-year capital facilities plan.
Construction could mean temporary closure of South Pioneer Way intersection next spring
MOSES LAKE — A new roundabout is tentatively scheduled for construction at the intersection of Yonezawa Boulevard and South Pioneer Way in spring 2027.