Two Quincy streets to be rebuilt, another gets repaved

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 4 years, 5 months AGO
by CHERYL SCHWEIZER
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | June 1, 2022 4:28 PM

QUINCY — Asphalt removal should begin sometime within the next couple of weeks on three blocks of B Street Northeast in Quincy.

“A complete new road,” said Shawn Pierce, project supervisor for Hurst Construction LLC.

B Street Northeast is one of two street improvement projects underway in Quincy this summer, and a third is nearing completion. Six blocks of B Street Northeast, between Central Avenue North and Sixth Avenue Northeast, are getting a rebuild.

Hurst, an East Wenatchee company, is the contractor for the $3.2-million project. Quincy city engineer Ariel Belino said the project will make major changes along B Street.

“We’re installing a new water line, we’re installing a new stormwater system,” Belino said.

B Street Northeast also will get new sidewalks, curbs and gutters on both sides of the street and a lighted pathway, Belino said. Construction crews were digging a trench for new electrical conduit Wednesday morning.

The stormwater system will make use of gravity to help drain runoff.

“They’re called infiltration galleries,” Pierce said. “Basically it’s a drain field, like a septic system, but on a much larger scale.”

Construction crews have installed the water lines and stormwater system from Third Avenue Northeast to Sixth Avenue Northeast. Once the electrical conduit is installed, the road will be graded and get a layer of gravel, then sidewalks will be installed, PIerce said.

Once the underground work and roadbed grading is completed, crews will move on to the Central-to-Third-Avenue section.

“We didn’t want to disturb all of the street at once,” Pierce said.

The work starts with asphalt removal, then the underground infrastructure will be installed. Sidewalks and gutters come next, and the entire six blocks will be paved at the same time.

“The asphalt will be the very last thing to go down,” Pierce said.

The project must be completed by October.

J Street Southwest will be repaved between 7th Avenue Southwest and 10th Avenue Southwest. The total project cost is about $973,000, Belino said.

‘It’s basically roadway resurfacing,” Belino said.

It will also include the installation of new ADA sidewalk ramps, crosswalks and stormwater catch basins. Hurst Construction is also the contractor for that project.

The section of A Street Southeast that was upgraded is home to a number of Quincy businesses, including a food processor and a farm chemical supplier. A Street Southeast got new and bigger water and sewer lines, was paved and got new curbs and gutters. A sidewalk was added in the area around the tennis courts and baseball and softball fields behind Quincy Middle School.

The total project cost was about $1.6 million, Belino said.

The three projects are part of ongoing efforts to repair streets in need of repair and to accommodate future growth, Belino said.

Road maintenance and improvement are a priority for the city.

“Every year when we have the money we’re redoing roads that need some work,” Belino said.

Cheryl Schweizer may be reached at [email protected].

photo

CHERYL SCHWEIZER/COLUMBIA BASIN HERALD

Construction workers dig trenches and water the road to relieve dust while working on B Street Northeast in Quincy Wednesday.

photo

CHERYL SCHWEIZER/COLUMBIA BASIN HERALD

B Street Northeast in Quincy is closed to through traffic while it’s under construction.

ARTICLES BY CHERYL SCHWEIZER

North Cascades Highway closed, possibly for the winter
November 26, 2026 8:10 p.m.

North Cascades Highway closed, possibly for the winter

WINTHROP — Snow slides along the North Cascades Highway closed the road early Thanksgiving evening, but Washington Department of Transportation officials aren't sure yet whether the road will be closed for the winter.

Water, sewer, parks improvements in Othello capital projects plan
November 27, 2026 1:25 a.m.

Water, sewer, parks improvements in Othello capital projects plan

OTHELLO — Upgrades to the heating-cooling system at Othello City Hall, a new shelter in Lions Park and upgrades to sections of 14th Avenue are among the possible projects for 2027 included in the city's six-year capital facilities plan.

Construction could mean temporary closure of South Pioneer Way intersection next spring
November 27, 2026 3:30 a.m.

Construction could mean temporary closure of South Pioneer Way intersection next spring

MOSES LAKE — A new roundabout is tentatively scheduled for construction at the intersection of Yonezawa Boulevard and South Pioneer Way in spring 2027.