QVMC contractor selection could start by mid-December
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 3 years, 4 months AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | November 29, 2022 4:22 PM
QUINCY — A request for bids from construction firms to build the new Quincy Valley Medical Center could be issued by mid-December. In addition, QVMC board members are scheduled to vote on a resolution to sell the bonds to finance the project at the Dec. 19 meeting. Hospital board members received an update on the project at the regular meeting Nov. 28.
Joe Kunkel, the consultant working with QVMC officials on the project, said hospital officials will make a presentation Dec. 1 to the Capital Projects Advisory Review Board, asking that the hospital district be allowed to waive some of the requirements of the bid process. If the request is allowed, the district will be able to hire a contractor immediately, Kunkel said.
“We’ll do a 20-minute presentation, then they get to pepper us with questions for 20 minutes, and they vote on the spot,” Kunkel said. “So I’m very confident that our application will be approved - there’s no reason that it shouldn’t be approved. But until it’s done, it’s not done.”
The district will have the option to reapply if the original request is rejected.
“If they say no, then we would get on to the next hearing because they would say no for a reason,” Kunkel said. “And we would address that, if they say, ‘Well, we weren’t comfortable with this part of your application.’”
If the application is approved, Kunkel said the request for proposals from contractors will be issued immediately.
“Then our selection committee will go through a process of finding a general contractor. And we continue to get a lot of interest around this project,” Kunkel said.
A consultant has been hired to evaluate the hospital’s existing equipment and determine what will still be usable in the new hospital. Hospital officials, staff and architects on the project will be working with scale models of the possible design to come up with ideas on how the building will fit together, Kunkel said.
“We’re going to start the blocking and stacking, (determining) relationships of ER to (diagnostic) imaging to wound care to the clinics, all those parts and pieces. We’re going to start playing with those things on site, and try to maximize those things. Which is very exciting - this is some of the most fun, because we’ll do some actual tabletop (designs) with scaled (models) and we’ll start to move them around.”
Hospital district residents approved a construction bond for the project in August, authorizing up to $55 million. Jim Nelson, senior vice president for D.A. Davidson, a district consultant on financing, said the plan is to sell about $46 million of the bonds in February 2023. The rest would be sold in January 2024 or January 2025.
He estimated property owners would pay about 43 cents per $1,000 of assessed property value in the first year of the bond, with rates projected to go up to 48 cents per $1,000 in the third year, dropping after that to about 41 cents per $1,000.
If the hospital board approves the bond resolution Dec. 19, the project will be submitted to bond rating agencies for their review in early January, Nelson said.
Cheryl Schweizer may be reached at [email protected].
ARTICLES BY CHERYL SCHWEIZER
Road closures, roundabout, mean construction season underway
EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”
Ybarra announces run for Washington Senate
QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.
Othello Community Museum to open April 25
OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.