QVMC design coming in early May

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 3 years, 5 months AGO
by CHERYL SCHWEIZER
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | April 3, 2023 5:03 PM

QUINCY — Details of the design for the new Quincy Valley Medical Center are starting to take shape. Architects and construction experts are still working to nail down costs, said Joe Kunkel, the consultant working with QVMC on the project.

Kunkel said the design team had to make some revisions, but the new building’s size has been pretty well established.

The current design calls for eight inpatient beds, he said. A proposed design should be ready for district patrons to see by early May.

“Right now we’re sitting at just about 49,000 square feet, which is really about where we wanted to be,” Kunkel said. “I think the master facilities plan was 47,000 (square feet) and change, so I think we’re pretty darn close, and have been able to hold on to most of the important things we wanted.”

Hospital officials had added some services, a small pool in the physical therapy department being one example, which added to the square footage requirements. Some of those may be included in the final design, but they might not, depending on the cost.

Kunkel gave an update on the project at the March 27 meeting of the hospital commissioners.

“Right now you’re talking, on average, direct construction (costs of about) $760, $755 per square foot, so all this stuff adds up pretty quickly,” he said.

Design meetings are held weekly, Kunkel said, and cost is a focus at each gathering.

“We’ve got some ideas of places that we were trying to realize some cost savings,” he said. “Every week we are reviewing a handful of those.”

Architects have worked out the size of each department, and how they fit together within the building. Now the design team is working on the layout of specific rooms, he said, such as the location of electrical receptacles and storage cabinets.

Part of that process is building full-size replicas of the rooms so QVMC employees can walk through them and see if the proposed design actually works, Kunkel said. Employees were working through that process last week.

The design team will be hiring construction managers for the electrical and mechanical systems, he said.

“This will help us with our (cost) estimating, as these will be the people who are actually doing the work,” he said. “It helps us especially on this project because your construction time is short. We’re talking right now that your direct construction time could be 15 (to) 16 months.”

Some components of those systems will take a while to arrive after they’re ordered, Kunkel said, so it’s important to get them ordered early. Having contractors focusing on those systems will speed up that process.

Cheryl Schweizer may be reached at [email protected].

New QVMC basics:

About 49,000 square feet

$755-$760 per square foot

Funded at 39 cents per $1,000 of property value in the district

Total cost estimated at $36 million in mid-March

Max bond authorization for the project: $55 million

Architect: Trinity:NAC of Spokane ($3.29 million)

Cumming Corporation – Design/Construction review ($23,500)

General Contractor: Graham Construction and Engineering

SOURCE: Grant County Hospital District 2

ARTICLES BY CHERYL SCHWEIZER

Road projects on hold for Labor Day weekend
September 4, 2026 3:10 a.m.

Road projects on hold for Labor Day weekend

MOSES LAKE — With Labor Day weekend dead ahead, drivers will be able to move freely about the state. Most road projects are on hold for the holiday weekend. Nobody will be working on the Hansen Road overpass on Interstate 90, but the lane restrictions that are in effect will continue through the end of the project.

Cost estimates for water source alternatives given to Moses Lake City Council
September 3, 2026 3:50 a.m.

Cost estimates for water source alternatives given to Moses Lake City Council

Protected under the U.S. Endangered Species Act, efforts are ongoing to keep it self-sufficient

MOSES LAKE — It’s going to cost a lot of money to provide alternative water sources for the city of Moses Lake, but some of the possible alternatives will cost more than others. City officials provided the Moses Lake City Council with costs for various alternatives Tuesday.

Dryer vent cleaning is important -- but often overlooked
September 4, 2026 1:20 a.m.

Dryer vent cleaning is important -- but often overlooked

MOSES LAKE — Not all the maintenance a house needs is visible. Sometimes a potential problem just goes unnoticed until it causes trouble, sometimes serious trouble. But a lot of potential problems give off warning signs. Clothes dryers often do when they need a good cleaning.