KCFR's new Station 4 opening pushed back
BILL BULEY | Hagadone News Network | UPDATED 1 year, 9 months AGO
Bill Buley covers the city of Coeur d'Alene for the Coeur d’Alene Press. He has worked here since January 2020, after spending seven years on Kauai as editor-in-chief of The Garden Island newspaper. He enjoys running. | April 14, 2023 1:09 AM
COEUR d’ALENE — The opening of one of Kootenai County Fire and Rescue’s new stations has been pushed back about a year.
But Fire Chief Chris Way is confident the scaled-back Station 4 at the Kootenai County Fairgrounds will remain on schedule.
“We’re back on track,” he said in a recent interview with The Press.
He said they initially estimated the 13,500-square-foot station could be built for $3.9 million, about $250 a square foot.
The lowest bid, however, came in at well over $300 a square foot.
“We had to revise the plan,” Way said.
The size of the station was reduced to about 9,500 square feet by eliminating one of three apparatus bays, training space, two rooms and two bathrooms.
“We retooled it to come back at $3.9 million,” Way said.
Way said the new station will provide better coverage of Dalton Gardens, Fernan and east of Coeur d’Alene.
The underground utility work for Station 4 is completed and it is now projected to open next spring.
It had been initially planned to open this summer.
Construction should begin soon.
“People want to see walls and we are in the same boat,” he said.
The station was designed by Miller Stauffer Architects and will be built by Ginno Construction.
The current Station 4 by the Kroc Center is nearly 50 years old and will be closed and sold.
The project is being funded by a $15 million general obligation bond that received 78% voter approval, 6,252 yes to 2,856 no votes, May 18, 2021.
Way said they have a responsibility to build within the bond amount approved by taxpayers.
He said like most construction projects during the pandemic, costs unexpectedly rose.
“We still have to build the other stations,” he said.
The bond also calls for a new Station 3 at Charleville and Prairie Avenue.
A new Station 5 will be built on Seltice Way by KCFR's training center.
Both are in different stages of planning and design.
KCFR is also moving today into temporary space at its training center while its new headquarters is built.
This is not part of the bond, Way said, but was funded by the sale of the old headquarters and other property.
ARTICLES BY BILL BULEY
Coeur d'Alene councilor says progress being made on housing
But City Councilor says there is still much work to do
Miller gave a presentation on housing issues before about 25 people at a gathering of Kootenai Strong, a new non-partisan community group.
Fernan Lake plan gains support
If funding of a few million is found, improvements could soon follow
Fernan Lake has experienced poor water quality for decades. It flushes well from winter to spring, but little flow occurs in the summer. That leads to an increase in nitrogen and phosphorus in the lake, which causes algae blooms comprised of toxic cyanobacteria.
Centennial Trail change in Coeur d'Alene OK'd
ITD plans to realign part of pathway as part of I-90 widening project
City Engineer Chris Bosley said ITD is looking to place a large swale in the area where the trail is located east of Atlas Way to accommodate stormwater from the I-90 widening that has reached a stage of seeking bids