QVMC site prep to begin in September
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 2 years, 8 months AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | August 3, 2023 5:17 PM
QUINCY — Demolition of existing structures and site preparation for the new Quincy Valley Medical Center will begin in mid-to-late September. Quincy hospital board members approved authorization for the contractor, Graham Construction, to start the first phase of the project. The cost of the first phase is $3.2 million.
Kayla Van Lieshout, project manager for the Klosh Group, one of the consultants, said the contractors will be asking for approval for two additional phases.
“We’ve decided to do some breakout packages to do some early work,” Van Lieshout said. “That allows us to start early (and) it also allows us to start procurement on some materials.”
The authorization, approved at a special meeting Wednesday, will allow crews to work on demolishing two existing buildings on the site, as well as a manufactured home that was used as administrative offices. It also allows the contractors to order equipment that will take a long time to build, including sections of the heating-cooling and electrical systems. Joe Kunkel, the lead consultant on the project, said those components are custom builds.
The areas slated for demolition are being cleaned out now, which is the reason there’s a garbage container outside one of the buildings, Kunkel said.
Cost for the second authorization is estimated at $4.4 million. Van Lieshout said that will pay for pouring and preparing the foundation, buying the structural steel, working on the fire protection system and the building’s elevator. That should be ready by early September, she said.
The final authorization will be the rest of the cost for construction, estimated at about $30.5 million. It’s called the “guaranteed maximum price” and should be submitted for authorization in late October, Van Lieshout said.
Kunkel estimated construction could start sometime in November.
The total construction cost will be about $38 million. Quincy Hospital District voters approved a $55 million bond for construction in August 2022. The rest of the bond money, about $17 million, will pay for things like medical equipment.
During the design process, hospital officials decided to add a hydrotherapy pool in the physical therapy department as well as an infusion suite. Kunkel said those will be paid for out of interest earned from the construction bonds. The cost for both was estimated at about $675,000.
Van Lieshout said the only thing that could change the estimated cost is if there are changes to the project. As an example, she said the discovery of hazardous materials during demolition would require an adjustment to the project and the budget, a procedure called a change order.
Kunkel said the work will start once the project permits are issued by the city of Quincy, a process that should be complete for the first phase by mid-September. It could take a little longer than that, but he said he expected the project to be cleared for demolition by the end of September.
Cheryl Schweizer may be reached at [email protected].
ARTICLES BY CHERYL SCHWEIZER
Road closures, roundabout, mean construction season underway
EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”
Ybarra announces run for Washington Senate
QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.
Othello Community Museum to open April 25
OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.