Port of Othello secures CERB funding for new water tower
GABRIEL DAVIS | Hagadone News Network | UPDATED 2 years, 4 months AGO
Gabriel Davis is a resident of Othello who enjoys the connections with his sources. Davis is a graduate of Northwest Nazarene University where he studied English and creative writing. During his free time, he enjoys reading, TV, movies and games – anything with a good story, though he has a preference for science fiction and crime. He covers the communities on the south end of Grant County and in Adams County. | August 8, 2023 5:29 PM
OTHELLO — The Port of Othello unanimously approved a resolution during Tuesday’s regular meeting to accept $5 million from the Washington Community Economic Revitalization Board for the installation of a new water tower on Port property at the north end of Bruce.
The Port secured the funding May 18, said Port of Othello Executive Director Chris Faix.
“What we’re adding is another 200,000-gallon steel elevated tank,” said Faix. “The Port owns 100 acres of light industrial ground where the tower’s going to go, so included in the project we’re going to put water piping around the 100 acres so that we can … loop the water tower with the existing system, that way we’ll provide potable water to that 100 acres, so that we can encourage more businesses to locate there.”
The Port owns and operates the water system in Bruce, according to the Port of Othello’s website, which includes a 200,000-gallon water tower already located on port property, as well as two wells. Faix said that the funding comes in the form of a $3.75 million low-interest loan and a $1.25 million grant.
“We have to pay the loan back, of course, but the way the funding works is you don’t have to start paying it back until…five years after the completion of the project. So it gives you a chance to start banking some money and hopefully, we’ll get that land up and going and moving in some customers who will use the water and help us make that payment.”
Faix said another reason the Port needs a new water tower is to increase the area’s water capacity for fire flow and fighting fires. He said that the port has enough water storage between the current tank and the two wells’ pumping capability, but not enough in the case of fires.
“The water tower was needed…or a lot of it was needed for fire flow so that if there happens to be a fire in Bruce at one of the places, we have enough fire flow for the fire department to fight the fire out there. That’s what made it a necessity to have,” said Faix.
That storage will also be used for future businesses, which Faix said the Port aims to bring in with the new tower.
“We’re looking to long-term lease it,” he said. “There is the option of buying it, but we’re leaning towards doing some long-term leases so we can boost the economy and bring some jobs to the area.”
Faix said there is still paperwork on the funding, but that a safe estimate of when the project will be done is two years. The Port is using J-U-B Engineers, Inc., of Kennewick.
“J-U-B’s already started some of the initial work,” said Faix. “We’re ready to hit the ground running and continue this project and get that tower built and get that pipe in the ground so we can get some businesses located there as soon as possible.”
Gabriel Davis may be reached at [email protected].
ARTICLES BY GABRIEL DAVIS
Work-based learning lets students build their own futures
MOSES LAKE — Work-based learning provides education opportunities for the workforce to receive hands-on training and technical education and prepare themselves to enter various industries. Educators and workforce development professionals from Eastern Washington discussed some the training they offer and the benefits of their programs. Next Generation Zone, an affiliate of WorkSource based in Spokane, provides job training opportunities for youth and young adults ages 16 to 24. Program Coordinator Kate Martin said there are multiple benefits to the program. “One of them is a paid work experience, and that’s where we reach out to area employers who are willing to take a young person and train them,” she said. “This is a short-term learning experience, so it’s typically about 240 hours; sometimes it could be longer or shorter. We’re the actual employer; we cover all of their wages, taxes, the L&I, and the employer just agrees to give them the experience and train them in whatever field it is that they’re wanting to go into.”
Serving schools: ESD superintendents reflect on operations, priorities
MOSES LAKE — Educational service districts are government-mandated agencies put in place to provide services to school districts across the state. ESD Superintendents discussed what they do and their priorities in operating their districts. ESD 105, led by Superintendent Kevin Chase, serves four counties, including Kittitas, Yakima and portions of Klickitat and Grant counties and provides support for 25 school districts – including Royal School District and Wahluke School District – and more than 66,000 students. “We help them collaborate with each other as well or collaborate with other partners,” Chase said. “(It’s) a lot of advocacy work, either regionally or across the state, or even federally, working on different issues that impact our education. And we provide very specialized services in certain situations in order to meet the needs of our students in our region and of our school districts.”
Columbia Basin Project making headway through Odessa Groundwater program
CASHMERE — The Columbia Basin Project is making gradual progress toward completion with particularly significant accomplishments for the Odessa Groundwater Replacement Program in the last six months or so, according to Columbia Basin Development League Executive Director Sara Higgins. “When we’re dealing with a project of this size, advancement is kind of like watching paint dry, but yes, there have been (developments),” she said. “There are a lot of exciting things happening right now.” There are more than 300 miles of main canals, about 2,000 miles of lateral canals and 3,500 miles of drains and wasteways in the irrigation project, according to the U.S. Bureau of Reclamation website. The CBDL advocates for the operation of those waterways and for the project to continue “build-out.”