Group 14 major equipment installation underway

GABRIEL DAVIS | Hagadone News Network | UPDATED 2 years AGO
by GABRIEL DAVIS
Gabriel Davis is a resident of Othello who enjoys the connections with his sources. Davis is a graduate of Northwest Nazarene University where he studied English and creative writing. During his free time, he enjoys reading, TV, movies and games – anything with a good story, though he has a preference for science fiction and crime. He covers the communities on the south end of Grant County and in Adams County. | December 18, 2023 3:45 PM

MOSES LAKE — Moses Lake’s Group 14 BAM-2 plant began installing equipment in its first module, topped out its second module, and is on track to ship its SCC55 silicon-carbon composite anode globally in 2024, according to a Dec. 18 announcement from the organization. 

The statement said that earlier this month, equipment installation commenced at the factory’s initial production module, keeping the plant on schedule to manufacture and ship SCC55 from the upcoming factory and meet global demand in 2024. 

“Keeping our pace of construction before the year ends, we also topped out the steel structure for the factory’s second module,” the statement said. “This comes just weeks after completing the steel structure of our first BAM-2 module. The team continues to move fast and we can’t wait to share our next stages of progress.”

According to the announcement, Group 14 also gave an onsite tour of BAM-2 to the U.S. Department of Energy’s Office of Manufacturing & Energy Supply Chains, whose Director Giulia Siccardo and Deputy Director David Howell met with Group 14 CEO Rick Luebbe and COO Eric Robinson.

“Siccardo and Howell’s visit follows a history of generous support from the DOE — they were impressed to see our rapid trajectory and developments,” said the statement.

For more information, visit bam2.group14.technology.

ARTICLES BY GABRIEL DAVIS

Work-based learning lets students build their own futures
July 25, 2024 1 a.m.

Work-based learning lets students build their own futures

MOSES LAKE — Work-based learning provides education opportunities for the workforce to receive hands-on training and technical education and prepare themselves to enter various industries. Educators and workforce development professionals from Eastern Washington discussed some the training they offer and the benefits of their programs. Next Generation Zone, an affiliate of WorkSource based in Spokane, provides job training opportunities for youth and young adults ages 16 to 24. Program Coordinator Kate Martin said there are multiple benefits to the program. “One of them is a paid work experience, and that’s where we reach out to area employers who are willing to take a young person and train them,” she said. “This is a short-term learning experience, so it’s typically about 240 hours; sometimes it could be longer or shorter. We’re the actual employer; we cover all of their wages, taxes, the L&I, and the employer just agrees to give them the experience and train them in whatever field it is that they’re wanting to go into.”

Serving schools: ESD superintendents reflect on operations, priorities
July 10, 2024 1 a.m.

Serving schools: ESD superintendents reflect on operations, priorities

MOSES LAKE — Educational service districts are government-mandated agencies put in place to provide services to school districts across the state. ESD Superintendents discussed what they do and their priorities in operating their districts. ESD 105, led by Superintendent Kevin Chase, serves four counties, including Kittitas, Yakima and portions of Klickitat and Grant counties and provides support for 25 school districts – including Royal School District and Wahluke School District – and more than 66,000 students. “We help them collaborate with each other as well or collaborate with other partners,” Chase said. “(It’s) a lot of advocacy work, either regionally or across the state, or even federally, working on different issues that impact our education. And we provide very specialized services in certain situations in order to meet the needs of our students in our region and of our school districts.”

Columbia Basin Project making headway through Odessa Groundwater program
June 25, 2024 1 a.m.

Columbia Basin Project making headway through Odessa Groundwater program

CASHMERE — The Columbia Basin Project is making gradual progress toward completion with particularly significant accomplishments for the Odessa Groundwater Replacement Program in the last six months or so, according to Columbia Basin Development League Executive Director Sara Higgins. “When we’re dealing with a project of this size, advancement is kind of like watching paint dry, but yes, there have been (developments),” she said. “There are a lot of exciting things happening right now.” There are more than 300 miles of main canals, about 2,000 miles of lateral canals and 3,500 miles of drains and wasteways in the irrigation project, according to the U.S. Bureau of Reclamation website. The CBDL advocates for the operation of those waterways and for the project to continue “build-out.”