Dodson Road project underway

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 1 year, 10 months AGO
by CHERYL SCHWEIZER
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | June 5, 2023 5:28 PM

EPHRATA — Drivers using Dodson Road between State Route 282 and Road 4 NW will be experiencing some delays as that section of the road gets a new layer of asphalt.

“It’s under construction right now,” said Grant County Engineer Dave Bren.

The 11-mile stretch of Dodson Road is the biggest road project in Grant County in 2023, he said. The bid for the project was about $3.2 million, with the county paying about $457,000 as its portion. Grant County received about $2.82 million in federal funding for the project. A one-mile section of the project is in the Ephrata city limits, so the city is paying about $264,000 for its portion.

Central Washington Asphalt is the contractor.

Chip-sealing of county roads also began this week. The chip-sealing program is set up so that each section of paved county road is chip-sealed every nine years, Bren said. Grant County is divided up into three road districts, and each district chip-seals about one-third of its roads every year.

“We’ve got a lot of road maintenance this summer. The chip-seal is road maintenance,” he said.

Other road projects originally planned for 2023 have been pushed back. The reconstruction of a section of Maple Drive NE and Grape Drive NE north of Moses Lake has been pushed back at least to 2024, and so has the construction of a roundabout at Road 12 SW and Dodson Road, northeast of Royal City.

Bren said the Maple Drive project is delayed because the county needs to complete acquisition of rights-of-way along the route.

“You have to work with private property owners,” he said.

Engineers are working on the project design. Maple Drive will be rebuilt between Stratford Road and North Hemlock Road, and Grape Drive between the Moses Lake city limits and its intersection with Maple.

County officials identified the Dodson Road-Road 12 SW intersection as one that needed some safety improvements, Bren said. The original plan was to build a full-size roundabout there, but county officials have decided to build what’s called a “compact roundabout.”

Bren said the roundabout at the Dodson Road-SR 282 intersection is an example. It’s smaller and lacks the mound in the center.

“The reason why is cost,” he said.

A compact roundabout is much cheaper, about $500,000 to $700,000, Bren said. County officials had applied for federal funding for the project, but didn’t receive it.

The Road 12 SW-Dodson Road intersection has been subject to a number of safety improvements in the past few years, including rumble strips in both directions on Road 12 SW, stop signs with flashing lights and a flashing yellow light on Dodson Road.

“We’re still having stuff happen,” Bren said.

Building the compact roundabout will mean the speed limit at the intersection will be reduced to 30 to 35 miles per hour.

“It’s a safety reason, is why we’re reducing the speed,” he said.

Cheryl Schweizer may be reached at cschweizer@columbiabasinherald.com.

photo

COURTESY IMAGE/GOOGLE

The intersection of Dodson Road and Road 12 SW will be converted into a roundabout over the summer.

MORE STORIES

Roundabout planned near Royal City
Columbia Basin Herald | Updated 1 year, 1 month ago
ROAD REPORT: Paving crews head north on SR 17
Columbia Basin Herald | Updated 10 months, 3 weeks ago
Road work to begin on Route 282 in Ephrata
Columbia Basin Herald | Updated 4 years, 10 months ago

ARTICLES BY CHERYL SCHWEIZER

Workshop Tuesday to discuss possible revisions to downtown Moses Lake streets
April 25, 2025 1:20 a.m.

Workshop Tuesday to discuss possible revisions to downtown Moses Lake streets

MOSES LAKE — Moses Lake residents are being invited to discuss a project that may mean some revisions to Third, Fourth and Fifth avenues, as well as roundabout at the intersection of Wheeler Road and Road L Northeast. The open house is scheduled for 5 to 7 p.m. April 29 at the Moses Lake Civic Center auditorium, 401 S. Balsam St.

Moses Lake, Warden residents arrested on drug, weapons charges
April 25, 2025 1:20 a.m.

Moses Lake, Warden residents arrested on drug, weapons charges

MOSES LAKE — Two Moses Lake and two Warden residents are in federal custody in connection with multiple investigations by the Moses Lake Police Department and two federal agencies into drug trafficking and firearms violations.

Apple prices, production costs make for hard decisions
April 24, 2025 1 a.m.

Apple prices, production costs make for hard decisions

QUINCY — When seen from the orchard, the state of the apple business is a little unsettled. Kent Karstetter, co-owner of RJK Farms near Quincy, said it requires growers to do some hard thinking and make some hard decisions as the 2024 crop goes to market. “Anymore, you look at your varietal mix, meaning what varieties you have. You look at the prices that you got and the size of the crop,” he said. “And then you figure, do you want to keep (a specific variety) for another year, or are you better off to try something different?” Trying something different would mean tearing out the existing trees and planting something else, grafting new varieties on the roots – or leaving that acreage empty.