Installation of Othello playground to begin

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 1 year, 7 months AGO
by CHERYL SCHWEIZER
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | June 27, 2023 4:50 PM

OTHELLO — The long-running project to build a new playground and expanded basketball courts in Othello’s Lions Park should be completed by this fall.

“We’re going to have (a playground) this year,” said Othello Mayor Shawn Logan Tuesday. Othello City Council members approved a contract for about $289,900 with PMOW LLC, Auburn, for site work and landscaping. City Engineer Shawn O’Brien said city officials already have purchased the playground equipment.

“(The PMOW contract) will prepare the area, both where the playground equipment will go and the concrete sidewalk that will surround it, and the landscaping outside that,” O’Brien said.

Logan said the contractor has 20 days to start the work, and 50 days after that to finish it. It’s the second phase of the three-phase playground project, Logan said; installation is the final phase.

Othello council members awarded the bid for the new basketball courts May 22, adding the option of lights that can be adjusted to light up two or all four courts.

“I’m so excited to see those basketball courts. And to play on them,” said council member Jon Erickson.

The playground project first was discussed in 2019, with the city applying for and receiving grants to pay for the bulk of the project. The coronavirus pandemic delayed design and construction, and costs increased in the meantime.

City officials initially received about $1.1 million in grants from the state Recreation and Conservation Office, along with about $100,000 in city funds and some local donations. The city also received about $600,000 in the Washington Senate capital budget, requested by 15th District Senator Nikki Torres.

Council members also voted to allocate funds from the city’s American Rescue Plan (ARPA) appropriation to pay for portions of the project. The basketball court lighting will add about $118,000 to the total cost of the basketball courts and will be paid for through ARPA funds.

“We overcame all those obstacles,” Logan said.

The new “Lions Pride” playground will include new swings and climbing bars. The park will be set up in two sections, one for children five years of age and younger, with toys for babies and toddlers, the second for children six years of age and older. There are special toys for children with limited mobility. The playground will have additional benches, picnic tables and trees, as well as sidewalks and walking paths.

“The community is going to have this playground for decades to come,” Logan said.

Cheryl Schweizer can be reached via email at cschweizer@columbiabasinherald.com.

P(L)aying the bill:

Rec & Conservation: $1.1M

City of Othello: $100,000

State budget: $600,000

American Rescue Plan: $118,000

MORE STORIES

Othello approves playground install, discusses ACPR contract
Columbia Basin Herald | Updated 1 year, 6 months ago
Othello playground design could begin this month
Columbia Basin Herald | Updated 2 years, 3 months ago

ARTICLES BY CHERYL SCHWEIZER

Revised Washington law makes it easier for youth to get identification
January 31, 2025 1:50 a.m.

Revised Washington law makes it easier for youth to get identification

OLYMPIA — It will be easier for young people 16-18 years of age to get a Washington identification card without a parent’s or guardian’s signature under revisions to ID laws that took effect Jan. 1.

Negligent driving law revisions add penalties in some cases
January 31, 2025 1:20 a.m.

Negligent driving law revisions add penalties in some cases

MOSES LAKE — Drivers will be subject to new penalties if they are charged with negligent driving in collisions that involve people who aren’t in a car or truck.

One infrastructure project complete, others planned for Royal City
January 30, 2025 1:05 a.m.

One infrastructure project complete, others planned for Royal City

ROYAL CITY — Cross one long, long project off the list. The last section of old water line in Royal City was replaced in 2024, wrapping up a project that Mayor Michael Christensen said took a while. “Over the years we’ve been trying to upgrade our water system, and now the entire city is upgraded,” Christensen said. “That was a long time coming and it was a bit of a task.”