Final Quincy hospital contract consideration postponed
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 2 years, 11 months AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | September 26, 2023 5:27 PM
QUINCY — The approval of the last — and largest — contract for the construction of the new Quincy Valley Medical Center is scheduled for Oct. 30.
Joe Kunkel, a consultant working with QVMC on the project, said Monday the hospital board originally was scheduled to approve the contract for the third phase of the project during Monday’s meeting. But waiting a month was determined to be the better option, he said.
“We said, ‘Let’s take a little more time and let the market work on this.’ Because if we try to jam it through, we’ll get a lot of people not responding. And we need as many eyes as we can get on this thing,” Kunkel said.
The third phase was projected in August to be about $38.5 million, and Abram Jenks, also a consultant on the project, said that’s still the estimate.
Graham Construction, Spokane, the general contractor on the project, and the subcontractors have advertised for bids on many of the materials, bids that will be opened Oct. 17.
“The 17th is a big day. It’s a milestone for sure,” Kunkel said.
The estimate that will ultimately be approved by the hospital board should be submitted for review by Oct. 20, Jenks said.
“Ideally, it’s under budget, and it’s a very quick review, some clarifications and we’re moving forward. We have some additional time in here because sometimes they’re not under budget,” Jenks said.
Some portions of the project are in need of adjustment to get them back within budget, he said.
Materials in the bid package range from masonry and window shades to roofing, wall and floor tiles and landscaping. Kunkel said the contractors want to have multiple bidders for each item.
Construction trailers are scheduled to start appearing on the site next Monday, Jenks said. The first task will be clearing the site of trees that have been cut down already, then demolishing what were the administrative offices, a converted manufactured home. The next step will be demolishing three additional buildings on the site.
When the demolition is completed crews will start installing underground utilities and preparing to pour the building foundation footings. Jenks said that work will be ongoing through early November.
The plans for the foundation are under review by the city of Quincy, and those plans must be approved before the footings and foundation can be installed.
“They can dig the footings, they can do the ground improvement, (but) our agreement with the city is you cannot pour the concrete, because that is when we need the foundation submittal approved,” Jenks said.
Cheryl Schweizer may be reached via email at [email protected].
ARTICLES BY CHERYL SCHWEIZER
Road projects on hold for Labor Day weekend
MOSES LAKE — With Labor Day weekend dead ahead, drivers will be able to move freely about the state. Most road projects are on hold for the holiday weekend. Nobody will be working on the Hansen Road overpass on Interstate 90, but the lane restrictions that are in effect will continue through the end of the project.
Cost estimates for water source alternatives given to Moses Lake City Council
Protected under the U.S. Endangered Species Act, efforts are ongoing to keep it self-sufficient
MOSES LAKE — It’s going to cost a lot of money to provide alternative water sources for the city of Moses Lake, but some of the possible alternatives will cost more than others. City officials provided the Moses Lake City Council with costs for various alternatives Tuesday.
Dryer vent cleaning is important -- but often overlooked
MOSES LAKE — Not all the maintenance a house needs is visible. Sometimes a potential problem just goes unnoticed until it causes trouble, sometimes serious trouble. But a lot of potential problems give off warning signs. Clothes dryers often do when they need a good cleaning.