ROAD REPORT: Repaving work underway on Road H SE
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 2 years AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | August 16, 2024 1:40 AM
POTHOLES RESERVOIR — Drivers thinking of using Road H Southeast between Potholes Reservoir and Othello should be prepared for delays as the road gets rebuilt.
Grant County Engineer Dave Bren said work started earlier this month. The cost to rebuild 4.67 miles is about $2.8 million, with about $2.5 million from a federal grant. Road H Southeast runs south from State Route 252 near the Mardon Resort.
“It’s a collector and it’s used a lot,” Bren said, and as a result was eligible for federal funding.
The existing surface is being excavated, the roadbed rebuilt where necessary and the road repaved. Bren said some sections of the roadbed had settled, and when that happens the base layer in those sections be rebuilt.
County public works crews will start work before the end of August on Road G.7 Northwest south of Quincy. The road connects Road H Northwest to White Trail Road. About 2.2 miles will be paved.
The road will be converted from gravel to pavement. Bren said crews will grade the existing road, add more base material if necessary, then two layers of asphalt and rock. It’s known as a gravel to oil project.
Estimated cost is about $400,000.
“All local funding,” Bren said.
County crews have other demands on their time and equipment, Bren said, and Road G.7 was scheduled after other projects were completed.
“When you’re doing gravel to oil, you have to wait until the equipment is available,” he said.
County crews are chip-sealing roads south of Warden and east of State Route 17. The work started earlier this week and is scheduled to last about two weeks. Chip-sealing is complete for the year along roads near Royal City.
A project earlier this summer to widen and repave roads around the Gorge Amphitheater is working as planned, Bren said, although the full effect won’t be felt until work on the Vantage Bridge is completed.
Sections of Silica Road and West Baseline Road were widened and turning lanes added. Road 1 Northwest was resurfaced. Bren said the project, along with improved security measures at the amphitheater, have made driving easier around the area on concert weekends.
The work on the Vantage Bridge has the effect of spreading out the traffic heading to the Gorge, he said, so the full impact of the road improvements won’t be felt until that project is done.
About one more week of work is left on a chip-sealing project along State Route 26 from Vantage to Royal City. Drivers can expect pilot cars and flagger-controlled traffic through the work zone, wrote Sebastian Moraga, Washington Department of Transportation public information officer, in an earlier press release.
Crews will be adding the finishing touches, such as striping, to SR 26 and other chip-seal projects in Grant, Chelan, Douglas and Okanogan counties throughout the rest of the summer, Moraga said.
A six-month project to remove some of the rocks along the cliff north of Soap Lake along SR 17 is scheduled for completion at the end of the month. Since February crews have been removing loose rocks, bolting rocks to the cliff face and installing steel nets to catch loose rocks. Traffic restrictions remain in place until the work is done.
Traffic is subject to 20-minute delays through the work zone. Drivers are stopped for 20 minutes, traffic goes through in each direction, then the road is closed for 20 minutes. Loads more than 12 feet wide are prohibited during work hours.
Speaking of the Vantage Bridge, work on replacing the bridge deck will continue through October. Traffic is restricted to one lane around the clock Monday through Friday. That will change after Labor Day, when traffic will be restricted to one lane on weekends as well as the work week. The bridge project is scheduled to take three years.
ARTICLES BY CHERYL SCHWEIZER
Road projects on hold for Labor Day weekend
MOSES LAKE — With Labor Day weekend dead ahead, drivers will be able to move freely about the state. Most road projects are on hold for the holiday weekend. Nobody will be working on the Hansen Road overpass on Interstate 90, but the lane restrictions that are in effect will continue through the end of the project.
Cost estimates for water source alternatives given to Moses Lake City Council
Protected under the U.S. Endangered Species Act, efforts are ongoing to keep it self-sufficient
MOSES LAKE — It’s going to cost a lot of money to provide alternative water sources for the city of Moses Lake, but some of the possible alternatives will cost more than others. City officials provided the Moses Lake City Council with costs for various alternatives Tuesday.
Dryer vent cleaning is important -- but often overlooked
MOSES LAKE — Not all the maintenance a house needs is visible. Sometimes a potential problem just goes unnoticed until it causes trouble, sometimes serious trouble. But a lot of potential problems give off warning signs. Clothes dryers often do when they need a good cleaning.