Samaritan construction remains on schedule, on budget

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 2 years AGO
by CHERYL SCHWEIZER
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | August 29, 2024 3:00 AM

MOSES LAKE — If construction of Samaritan Hospital stays on schedule, the first patients will be treated in the new facility in early March 2026.  

Joe Kunkel, a consultant on the project since its inception, told Samaritan commissioners Tuesday that planning for the move will start soon. 

“We’re not really into transition planning, but if the schedule (holds), 560 days from today we’ll be seeing our first patient,” Kunkel said. 

Consultants started meeting with department managers Wednesday to begin talking about the process of moving from one building to another. 

“When you think about that, that’s getting you ready to see patients in the new building,” Kunkel said. “Not only from a logistical standpoint, but it’s the training. It’s the clinical training, the workflow training and all the parts and pieces that go with it.” 

Department managers and staff are reviewing floor plans, room by room, Kunkel said, to see if equipment and furniture planned for each room is the right stuff.  

“We’ve done it a couple times already. This is our way of making sure that our equipment that we’re bringing over (from the existing facility) and what we’re ordering new is accurate,” Kunkel said.  

The review also provides a check on existing equipment, ensuring that what hospital officials were planning to reinstall in the new facility still works and doesn’t need replacement, he said.  

While it’s still about 18 months away, consultants and Samaritan staff are starting to talk about the actual move from Wheeler Road to Yonezawa Boulevard. Samaritan operations will shift from one location to another in one day.  

“I think there’s anxiety that happens when people start to think about, ‘How are we going to do this?’ How does a move day happen? How do you do that in a day? You do it in a day by preparing for a year,” Kunkel said.  

Samaritan staff will be involved in the planning, he said.  

It’s not just a matter of finishing construction and moving in — hospitals are subject to stringent regulation, and a number of agencies must issue licenses and permits before the building can be occupied. Kunkel listed some of them — construction reviews by the Washington Department of Health, and specific oversight agencies for specific departments like the pharmacy, the laboratory and imaging.  Kunkel said now is the time to start contacting the varying agencies and updating them on the project. 

“We want to get on their radar,” Kunkel said. 

Damon Gardella of the Klosh Group, part of the consultant team, said the interior fireproofing is almost done, which means interior framing can start going up throughout sections of the building where it’s been delayed. 

Employees of various departments throughout the hospital have been coming to the site to look at the actual space and review the proposed placement of equipment and materials, a process called a “box walk.” Gardella said those would continue through November.  

“They’ve been very helpful, very useful,” he said. 

Parking lots are being paved, Gardella said. Kunkel added that landscaping will start on some of the property in September.  

Construction remains on schedule and within the $225 million budget, Gardella said. 



 


ARTICLES BY CHERYL SCHWEIZER

Road projects on hold for Labor Day weekend
September 4, 2026 3:10 a.m.

Road projects on hold for Labor Day weekend

MOSES LAKE — With Labor Day weekend dead ahead, drivers will be able to move freely about the state. Most road projects are on hold for the holiday weekend. Nobody will be working on the Hansen Road overpass on Interstate 90, but the lane restrictions that are in effect will continue through the end of the project.

Cost estimates for water source alternatives given to Moses Lake City Council
September 3, 2026 3:50 a.m.

Cost estimates for water source alternatives given to Moses Lake City Council

Protected under the U.S. Endangered Species Act, efforts are ongoing to keep it self-sufficient

MOSES LAKE — It’s going to cost a lot of money to provide alternative water sources for the city of Moses Lake, but some of the possible alternatives will cost more than others. City officials provided the Moses Lake City Council with costs for various alternatives Tuesday.

Dryer vent cleaning is important -- but often overlooked
September 4, 2026 1:20 a.m.

Dryer vent cleaning is important -- but often overlooked

MOSES LAKE — Not all the maintenance a house needs is visible. Sometimes a potential problem just goes unnoticed until it causes trouble, sometimes serious trouble. But a lot of potential problems give off warning signs. Clothes dryers often do when they need a good cleaning.