Samaritan construction remains on schedule, on budget
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 1 year, 7 months AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | August 29, 2024 3:00 AM
MOSES LAKE — If construction of Samaritan Hospital stays on schedule, the first patients will be treated in the new facility in early March 2026.
Joe Kunkel, a consultant on the project since its inception, told Samaritan commissioners Tuesday that planning for the move will start soon.
“We’re not really into transition planning, but if the schedule (holds), 560 days from today we’ll be seeing our first patient,” Kunkel said.
Consultants started meeting with department managers Wednesday to begin talking about the process of moving from one building to another.
“When you think about that, that’s getting you ready to see patients in the new building,” Kunkel said. “Not only from a logistical standpoint, but it’s the training. It’s the clinical training, the workflow training and all the parts and pieces that go with it.”
Department managers and staff are reviewing floor plans, room by room, Kunkel said, to see if equipment and furniture planned for each room is the right stuff.
“We’ve done it a couple times already. This is our way of making sure that our equipment that we’re bringing over (from the existing facility) and what we’re ordering new is accurate,” Kunkel said.
The review also provides a check on existing equipment, ensuring that what hospital officials were planning to reinstall in the new facility still works and doesn’t need replacement, he said.
While it’s still about 18 months away, consultants and Samaritan staff are starting to talk about the actual move from Wheeler Road to Yonezawa Boulevard. Samaritan operations will shift from one location to another in one day.
“I think there’s anxiety that happens when people start to think about, ‘How are we going to do this?’ How does a move day happen? How do you do that in a day? You do it in a day by preparing for a year,” Kunkel said.
Samaritan staff will be involved in the planning, he said.
It’s not just a matter of finishing construction and moving in — hospitals are subject to stringent regulation, and a number of agencies must issue licenses and permits before the building can be occupied. Kunkel listed some of them — construction reviews by the Washington Department of Health, and specific oversight agencies for specific departments like the pharmacy, the laboratory and imaging. Kunkel said now is the time to start contacting the varying agencies and updating them on the project.
“We want to get on their radar,” Kunkel said.
Damon Gardella of the Klosh Group, part of the consultant team, said the interior fireproofing is almost done, which means interior framing can start going up throughout sections of the building where it’s been delayed.
Employees of various departments throughout the hospital have been coming to the site to look at the actual space and review the proposed placement of equipment and materials, a process called a “box walk.” Gardella said those would continue through November.
“They’ve been very helpful, very useful,” he said.
Parking lots are being paved, Gardella said. Kunkel added that landscaping will start on some of the property in September.
Construction remains on schedule and within the $225 million budget, Gardella said.
ARTICLES BY CHERYL SCHWEIZER
Road closures, roundabout, mean construction season underway
EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”
Ybarra announces run for Washington Senate
QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.
Othello Community Museum to open April 25
OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.