Friday, April 03, 2026
48.0°F

Multi-decade Grant PUD project three-quarters complete

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 2 years, 1 month AGO
by CHERYL SCHWEIZER
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | February 5, 2024 4:53 PM

EPHRATA — A decades-long project to upgrade turbines and generator units for both dams owned and operated by the Grant County PUD is three-quarters complete. Upgrades to the fifth of 10 generator-turbine combinations at Priest Rapids Dam are done.

Dale Campbell, senior manager of power production, said crews finished more than 30 days ahead of schedule, and have moved on to the next one.

“That unit is now mostly disassembled and it’s good we chose that unit,” Campbell said. “It was in really rough shape.”

Some pieces of the turbine were showing signs of wear; one had cracks that showed it was in danger of failing, he said. 

“(Upgrade work) is on track,” he said. “We got a little behind in the first month or so, but we’ve been able to make up time and we’re back on track.”

Work on Priest Rapids turbines and generators began in 2016, with the entire project scheduled for completion in 2030. Each unit takes about 14 months to complete, according to earlier interviews with PUD officials.

The work at Priest Rapids began after a similar project at Wanapum Dam, which started in 2004. The goal was to take advantage of upgraded technology and improve efficiency, and power production as a result, at both dams.

When it’s done the project will cost more than $1 billion, according to earlier estimates. 

Utility district officials set targets for various functions of dam operation, one of which measures how often equipment is working and not under repair. The power supply division met its target for all but two months of the year. Ben Pearson, senior manager of hydro generation, said the disruption in October and December was a transformer part. The problem also prompted a further review of those parts throughout the transmission system. 

“We discovered it during maintenance, and we decided to extend that outage to replace the (part),” he said. 

The part, a bushing, wasn’t broken, but it could’ve broken, and after finding one that was failing, PUD employees went through the records and found another that was showing signs of breaking down. If they failed, there could’ve been serious consequences, Pearson said.

“We didn’t want to risk a catastrophic failure — any explosion, fire, potentially,” he said.

The two potential failures prompted further review, Pearson said, since the bushings are about 10 years old. The parts also will be subjected to more scrutiny during maintenance.

“We’re sending at least one of these bushings back to a third-party vendor to do some forensics diagnostics,” he said. “We’re trying to figure out if maybe this is a problem with this type of bushing, this manufacturer of bushing — these are not expected to fail in 10 years of use. We’ve had three or four of these fail since we put these in service. These are fairly new transformers.”

Cheryl Schweizer can be reached via email at [email protected].

ARTICLES BY CHERYL SCHWEIZER

Road closures, roundabout, mean construction season underway
April 3, 2026 3 a.m.

Road closures, roundabout, mean construction season underway

EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”

Ybarra announces run for Washington Senate
April 2, 2026 1:48 p.m.

Ybarra announces run for Washington Senate

QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.

Othello Community Museum to open April 25
April 1, 2026 3:45 a.m.

Othello Community Museum to open April 25

OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.