Port of Warden requesting more funding for bypass road

GABRIEL DAVIS | Hagadone News Network | UPDATED 1 year, 10 months AGO
by GABRIEL DAVIS
Gabriel Davis is a resident of Othello who enjoys the connections with his sources. Davis is a graduate of Northwest Nazarene University where he studied English and creative writing. During his free time, he enjoys reading, TV, movies and games – anything with a good story, though he has a preference for science fiction and crime. He covers the communities on the south end of Grant County and in Adams County. | February 5, 2024 5:03 PM

WARDEN – Port of Warden Executive Director Pat Millard shared several updates regarding the port’s ongoing industrial bypass road project, primarily that the port will be requesting more funding for the bypass road during the current legislative session. 

Millard said the port will request the funding, likely $2.5 million, through Sen. Judy Warnick’s office, which will submit the request to the Senate Transportation Committee. Millard said she wasn’t sure of the likelihood of being awarded the money.

“I think it's purely going to depend on if they have the money,” Millard said. “I don't know if it's going to be in this session when they will send it on, so maybe the next session.”

The port was originally awarded $2.5 million in Federal Highway Administration Funding from the Consolidated Appropriations Act of 2023 for the road project, according to an April 2023 press release from the Port of Warden. 

The release stated that the project's purpose is to bypass trucks around residential neighborhoods to industrial-zoned properties on the south side of Warden. The road would intersect with State Route 170 next to the Grant County PUD substation and travel south toward property the port has yet to develop. 

“We had kind of a design, but it went through the residential area, and because there's so many trucks involved, companies didn’t want to go through residential areas, so we were able to go through where the PUD is,” Millard said. “But it has to go over the tracks, and Columbia Basin Railroad has finally given us permission to go over the tracks, so that will take us to our south property that we own … We hope to move some industries down there.”

Millard said the project has secured an engineer for the design. Western Pacific Engineering & Surveying was the only company to respond to the port’s notifications and requests for services. 

“The design will come and then we'll go on to the construction after that…It could be a while, but we've been working on this for a long time. It's probably been about three years,” Millard said. “We decided we needed to do something in order to open that land up for future development.”

Millard also provided an update on the original $2.5 million the port was awarded, 13% of which has to be matched by the port. 

“For the $2.5 million, we have gotten approval from (Washington State Department of Transportation), our person there, to move forward. So we're in the process of doing a sole-source (contract) and consultant agreement,” Millard said. “Once we get those done, they will go back to our person at WSDOT and be approved, and then we will move forward to the next step, which is probably getting the funds secured … We have the funding; we just have to go through the steps.”

Millard said it is too early to tell how long the design and construction processes will take for the road project, or predict when the project will be finished. She said it is taking longer than expected, but the port is still doing well in the meantime. 

“We're making progress,” she said. “It's just slow.”

Gabriel Davis may be reached at [email protected]. Download the Columbia Basin Herald app on iOS and Android.


    Exterior of the Port of Warden’s offices, located off State Route 170 as it enters Warden. The port will request more funding for an industrial bypass road that will intersect with 170 and lead to the port’s southern property.
 
 


ARTICLES BY GABRIEL DAVIS

Work-based learning lets students build their own futures
July 25, 2024 1 a.m.

Work-based learning lets students build their own futures

MOSES LAKE — Work-based learning provides education opportunities for the workforce to receive hands-on training and technical education and prepare themselves to enter various industries. Educators and workforce development professionals from Eastern Washington discussed some the training they offer and the benefits of their programs. Next Generation Zone, an affiliate of WorkSource based in Spokane, provides job training opportunities for youth and young adults ages 16 to 24. Program Coordinator Kate Martin said there are multiple benefits to the program. “One of them is a paid work experience, and that’s where we reach out to area employers who are willing to take a young person and train them,” she said. “This is a short-term learning experience, so it’s typically about 240 hours; sometimes it could be longer or shorter. We’re the actual employer; we cover all of their wages, taxes, the L&I, and the employer just agrees to give them the experience and train them in whatever field it is that they’re wanting to go into.”

Serving schools: ESD superintendents reflect on operations, priorities
July 10, 2024 1 a.m.

Serving schools: ESD superintendents reflect on operations, priorities

MOSES LAKE — Educational service districts are government-mandated agencies put in place to provide services to school districts across the state. ESD Superintendents discussed what they do and their priorities in operating their districts. ESD 105, led by Superintendent Kevin Chase, serves four counties, including Kittitas, Yakima and portions of Klickitat and Grant counties and provides support for 25 school districts – including Royal School District and Wahluke School District – and more than 66,000 students. “We help them collaborate with each other as well or collaborate with other partners,” Chase said. “(It’s) a lot of advocacy work, either regionally or across the state, or even federally, working on different issues that impact our education. And we provide very specialized services in certain situations in order to meet the needs of our students in our region and of our school districts.”

Columbia Basin Project making headway through Odessa Groundwater program
June 25, 2024 1 a.m.

Columbia Basin Project making headway through Odessa Groundwater program

CASHMERE — The Columbia Basin Project is making gradual progress toward completion with particularly significant accomplishments for the Odessa Groundwater Replacement Program in the last six months or so, according to Columbia Basin Development League Executive Director Sara Higgins. “When we’re dealing with a project of this size, advancement is kind of like watching paint dry, but yes, there have been (developments),” she said. “There are a lot of exciting things happening right now.” There are more than 300 miles of main canals, about 2,000 miles of lateral canals and 3,500 miles of drains and wasteways in the irrigation project, according to the U.S. Bureau of Reclamation website. The CBDL advocates for the operation of those waterways and for the project to continue “build-out.”