Friday, April 03, 2026
48.0°F

Grant County Jail construction second phase start dependent on permit approvals

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 2 years, 1 month AGO
by CHERYL SCHWEIZER
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | February 20, 2024 1:00 AM

EPHRATA — The first phase of construction of the new Grant County Jail — demolition and site preparation — was supposed to start next week, but cooperative weather meant the project actually started in late January. Grant County Central Services Director Tom Gaines said footings, foundations and walls tentatively are scheduled to start going up in March or April.

When foundations will start going in and walls going up depends on the approval of a state-required environmental review. That process is still ongoing.

“We’re digging the sewer line right now,” Gaines said. “A lot of the demolition is done.”

The new jail will be at the location of the old Ephrata Raceway, at the intersection of State Route 282 and Nat Washington Way. The track and pits, the bleachers, the announcer booth and the concession stand have all been removed. 

As an old racetrack the site had contaminated dirt that had to be removed, Gaines said, and all that work is completed too. 

The size of the new jail means installing a lot of sewer lines, Gaines said. Selland Construction is the contractor for the first phase, and the company’s crews also are laying water lines, a project that will involve tunneling under SR 282. The site also must be leveled before construction can begin. 

“They’ve still got quite a bit of work to do,” Gaines said. 

However, the site preparation triggered further review under the Washington State Environmental Policy Act, a process known as SEPA.

“The amount of dirt we have to move is what triggered the SEPA in the first place,” Gaines said.

The process requires review by other state agencies, which prompted a response from the Washington Department of Transportation. Under discussion is the proposed roundabout at the SR 282-Nat Washington Way intersection. A roundabout has been planned for that intersection for a few years, but no construction date has been announced. 

Department of Transportation officials were concerned about traffic impacts at specific times of day if the jail is completed before the roundabout, Gaines said. County officials proposed a mitigation plan, Gaines said, and are waiting for the WSDOT’s response.

Site preparation can continue, but SEPA approval is required before the foundation can be poured and the actual construction of the building can start, Gaines said.

Grant County residents approved a one-tenth of 1% increase in the sales tax for law and justice projects in 2019, with some of the proceeds going to the jail project. Grant County Commissioners approved the sale of up to $90 million in construction bonds in summer 2022. 

The design is still being reviewed but includes room for 512 inmates, with room for isolation for inmates suffering from communicable diseases and some space for inmates with mental or behavioral health challenges. The Grant County Sheriff’s Office also will move to the new facility. 

Cheryl Schweizer may be reached via email at [email protected].

    The old Ephrata Raceway grandstands come down at the site of the new Grant County Jail.
 
 


ARTICLES BY CHERYL SCHWEIZER

Road closures, roundabout, mean construction season underway
April 3, 2026 3 a.m.

Road closures, roundabout, mean construction season underway

EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”

Ybarra announces run for Washington Senate
April 2, 2026 1:48 p.m.

Ybarra announces run for Washington Senate

QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.

Othello Community Museum to open April 25
April 1, 2026 3:45 a.m.

Othello Community Museum to open April 25

OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.