Friday, November 27, 2026
37.0°F

Concrete next phase of QVMC construction

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 2 years, 9 months AGO
by CHERYL SCHWEIZER
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | February 27, 2024 6:25 PM

QUINCY — Construction crews will start pouring the concrete slab at the site of the new Quincy Valley Medical Center sometime next week. 

The steel supports for the first and second floors are going up, a process that requires a crane and one that project manager Joe Kunkel said is nearing completion.

“The next thing coming up will be when the crane leaves, you’ll see the concrete trucks coming in,” Kunkel said.

The concrete slab will be poured in sections, and should be completed by the end of March, Kunkel said. Abram Jenks of the Klosh Group, consultants on the project, said framing will begin once that’s done.

The work will continue despite some risk, which Kunkel said he thought was a slight risk but still a risk, posed by unfinished reviews by the Washington Department of Health. 

Typically DOH staffers review the design multiple times during construction, he said, but make one complete review and ask questions they have before construction begins. The QVMC project didn’t get that initial review due to DOH staffing shortages. 

“Normally, you get an authorization at the beginning of construction, after they’ve done their first set of reviews — which they gave us, but it was a limited one. They said, ‘Well, you can do site work and steel,’” Kunkel said.

That part of the project is nearing completion, he said. 

The DOH reviews multiple components of the project, from fire safety to mechanical and electrical systems. Department of Health officials then ask questions about the design, which are answered by the applicant, in this case, QVMC. 

“So then you resubmit (the plans) based on those comments. And then they go back through it again,” Kunkel said. 

That process usually takes multiple rounds of questions and answers, he said. In the case of QVMC, the process has stalled. Hospital officials held a meeting with DOH staffers Tuesday to answer the most significant questions from DOH. Kunkel said the contractors and architects believe they have satisfactory answers, and by Friday will have answers to all the questions they’ve been given so far.

“We think that the level of risk is minor and manageable,” Kunkel said.

The DOH can’t stop construction if they’re not done with the reviews, Kunkel said, and project managers don’t want to stop construction now that it’s started.

“You can (continue) at risk, or you can not (continue).” he said. “They can’t tell you to stop. They will tell you you’re responsible for things they haven’t reviewed.” 

The project is on schedule, said Jessie Steiger of the Klosh Group, although construction was delayed for a few days by bad weather in January. Hospital officials have received the building permit from the city. 

“That was a huge milestone,” she said.

Cheryl Schweizer can be reached via email at [email protected].

ARTICLES BY CHERYL SCHWEIZER

North Cascades Highway closed, possibly for the winter
November 26, 2026 8:10 p.m.

North Cascades Highway closed, possibly for the winter

WINTHROP — Snow slides along the North Cascades Highway closed the road early Thanksgiving evening, but Washington Department of Transportation officials aren't sure yet whether the road will be closed for the winter.

Water, sewer, parks improvements in Othello capital projects plan
November 27, 2026 1:25 a.m.

Water, sewer, parks improvements in Othello capital projects plan

OTHELLO — Upgrades to the heating-cooling system at Othello City Hall, a new shelter in Lions Park and upgrades to sections of 14th Avenue are among the possible projects for 2027 included in the city's six-year capital facilities plan.

Construction could mean temporary closure of South Pioneer Way intersection next spring
November 27, 2026 3:30 a.m.

Construction could mean temporary closure of South Pioneer Way intersection next spring

MOSES LAKE — A new roundabout is tentatively scheduled for construction at the intersection of Yonezawa Boulevard and South Pioneer Way in spring 2027.