Budget approved for first phase of new Othello animal shelter

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 6 months, 3 weeks AGO
by CHERYL SCHWEIZER
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | July 10, 2024 3:15 AM

OTHELLO — A new animal shelter is in the works for the city of Othello. The Othello City Council approved a $340,000 budget for the initial phase of the construction at its regular meeting Monday, after some discussion of options, landscaping, philosophy and cost. 

City Engineer Robin Adolphsen said the original plan was to buy a temporary facility that came with kennels, but the price of that made city officials reexamine that idea.

Othello had a contract for animal control services with Adams County Pet Rescue, with all animals housed at the ACPR facility. In January city officials opted to enter into an agreement with Hands ‘n Paws, Moses Lake.

“We have a temporary kennel set up,” Adolphsen said. “The agreement was that we would put a larger temporary facility together, and Hands ‘n Paws had looked at getting a temporary facility that was all-encompassed and it just would be delivered. And when we actually built that out to the specifications that were required, (the estimated cost was) $250,000. So if we’re going to spend $250,000 on a temporary kennel, we might as well look at what it’s going to take to put in a permanent shelter.”

City officials and Hands ‘n Paws operators discussed options and came up with a preliminary idea for the eventual shelter. The proposal, and the budget, approved by the council will build a first phase, however that looks.

Adolphsen said interested contractors will bid on two options. The first would build a structure with 12 kennels, six of which could be used for isolation, an office and two medical rooms to treat animals. In the first option, that section would be completed, from cement floors to ventilation, and could be expanded. 

The second option would be a structure big enough to accommodate all phases of the project, then finish as much of the inside as the remaining budget would allow, Adolphsen said. The council would decide how they wanted to proceed. 

Adolphsen said the estimated cost for a building that could accommodate the whole buildout was about $250,000. The new shelter will be located on city-owned land west of Broadway Avenue, said Mayor Shawn Logan in a later interview. 

The animal shelter was the subject of some discussion during the public comment period before the vote. Othello resident Ernie Summers said he was an ACPR advisor and a retired veterinarian; he thought the city was duplicating a service that already existed. He asked about financing. 

“I’d kind of like to know exactly where this $340,000 is coming from,” he said.

The negotiations with ACPR involved a much smaller amount, Summers said. He also asked if the city was considering the ongoing costs.

Logan said city officials were required to change some of the original plans for 2024 to accommodate the animal shelter.

“The city has had to cut projects in order to get this done,” Logan said. “There’s a list of projects that now are not going to be done because of this.”

It’s a new experience for the council and city officials as well, he said

“You’re asking all the questions that we’re asking ourselves. Phase One is expensive — is there a Phase Two, a Phase Three? Obviously, there’s going to be some more that’s going to need to be done,” Logan said.

During the public comment period, Othello resident Kim Bailey said city officials should allocate some money for landscaping.

“I just want to remind you what the previous dog pound looked like,” Bailey said. “Cinderblock building on a dirt lot.” 

Council member Mark Snyder asked if the existing temporary shelter was proving to be adequate for the demand. He asked if Othello needed an animal shelter as big as proposed (ultimately 32 kennels) if the temporary shelter was working. Logan said the city agreed to build a permanent shelter of that size. 

Council member John Lallas said he thought the city should clarify its role.

“There seems to be a misinterpretation,” Lallas said. “This is a shelter. It’s not a rescue. We’re taking these animals, putting them in the shelter (and) then shipping them out.” 

Council member Genna Dorow said Hands ‘n Paws ultimately would be responsible for any animals in the shelter. 

“We’re not involved with holding these dogs, saving these dogs, spending money on these dogs — and cats — in any way shape or form,” Lallas said. “There’s another entity involved.”

Logan said Othello residents have been volunteering to provide foster care. 

“You have members of the community that are stepping up because they love animals,” Logan said. 

Hands ‘n Paws will be responsible for veterinary care and adoption services, he said.

“That’s the new age of animal care, whether it’s a rescue shelter or our particular facility,” Logan said. “We’re looking at this humanely. We know we can’t save them all, but we’re going to save everything we can. That’s our philosophy in this process, and that’s (the) Hands ‘n Paws philosophy.” 

Cheryl Schweizer can be reached via email at cschweizer@columbiabasinherald.com.

    Adams County Pet Rescue had provided animal shelter services for Othello for quite a while but increasing operational costs got in the way earlier this year.
 
 


 

MORE STORIES

Hands 'N Paws says temp shelter doing well one month in
Columbia Basin Herald | Updated 10 months ago
Othello contracts with Hands 'N Paws
Columbia Basin Herald | Updated 11 months, 3 weeks ago
Othello Public Works set for a busy 2025
Columbia Basin Herald | Updated 1 day, 13 hours ago

ARTICLES BY CHERYL SCHWEIZER

One infrastructure project complete, others planned for Royal City
January 30, 2025 1:05 a.m.

One infrastructure project complete, others planned for Royal City

ROYAL CITY — Cross one long, long project off the list. The last section of old water line in Royal City was replaced in 2024, wrapping up a project that Mayor Michael Christensen said took a while. “Over the years we’ve been trying to upgrade our water system, and now the entire city is upgraded,” Christensen said. “That was a long time coming and it was a bit of a task.”

2024 projects, challenges continuing into 2025 in Quincy
January 30, 2025 1 a.m.

2024 projects, challenges continuing into 2025 in Quincy

QUINCY — Accommodating growth and upgrading infrastructure were the big challenges facing the city of Quincy in 2024, and they’re the challenges going into 2025. Quincy City Administrator Pat Haley said the city’s water and wastewater treatment facilities have been, and will continue to be, at the top of the agenda. “(Evaluating) what’s required in terms of growth and upgrades. Our facilities are aged, or at capacity, and that’s probably true for those cities of our size or communities that are growing,” Haley said. “So, we’re still pretty aggressively working on those things.”

Othello Public Works set for a busy 2025
January 29, 2025 1 a.m.

Othello Public Works set for a busy 2025

OTHELLO — Some long-term projects in Othello reached completion in 2024, and there’s a whole list of new projects planned for 2025. Public Works Director Robin Adolphsen summed it up. “There’s a lot going on,” she said. Summer 2024 saw the completion of a project that was first considered in 2019, the opening of the new Iron Horse playground in Lions Park. Most of the project was paid for with grants the city received from the Washington Recreation and Conservation Office and a capital appropriation from the Washington Legislature.