Major upgrades coming to Westshore Drive next summer

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 2 years, 1 month AGO
by CHERYL SCHWEIZER
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | July 23, 2024 1:30 AM

MOSES LAKE — Drivers who use Westshore Drive can get an overview of the work planned for spring 2025 along Westshore Drive, and get their questions answered, at a meeting scheduled for 7 p.m. Tuesday at the Moses Lake Country Club, 1373 at Road F.2 NE.

Grant County Engineer David Bren said work on Westshore that was planned for 2026 has been moved forward to 2025.

“Suddenly (funding) became very available, and we had to spend it right away,” Bren said.

The Moses Lake School District is purchasing property at the intersection of Westshore Drive and Road 4 NE to build a new elementary school, and a 2.12-mile section of Westshore leading to the school will get a major rebuild. The work is scheduled to begin in March 2025, with projected completion in July.

Total project cost is about $2.7 million. About $2.4 million will be paid through a federal grant, with about $300,000 paid by Grant County, Bren said.

That section of Westshore will be repaved, with curbs, gutters and sidewalks on both sides of the road and new crosswalks. The speed limit for that section will drop to 25 miles per hour, with radar enforcement and traffic signs announcing that. 

Bren said the goal is to improve safety along that section of Westshore, especially when children start walking and riding bikes to and from school. 

“The safety situation is going to fundamentally change with the new elementary school,” he said. 

County officials had obtained funding for improvements to Westshore a few years ago, but the initial funding was not enough, he said. 

“The costs have gone up for these projects,” he said, in some cases by as much as 40%.

County officials are working on a number of road projects for 2025, Bren said, most of which have been funded. But due to the nature of state and federal funding, projects can be rescheduled. Planned upgrades to sections of Grape Drive and Maple Drive north of State Route 17 are an example — they were scheduled for 2025, but have been moved back to 2026.

County officials have obtained federal funding for the replacement of Bridge 247 north of Warden. The bridge will be widened to allow widening of the irrigation canal it crosses, which will provide access to surface water to farmers further east, who now use groundwater for irrigation. 

The project cost a little more than $4 million, all paid for through a federal grant, Bren said.

Federal funds also are being used to pay the bulk of a project planned for Desert Aire Drive next year. Bren said it too is designed to improve pedestrian safety, since the road gets a lot of pedestrian use.

“We’re going to have a separate gravel trail, so we can separate the people and the cars,” he said. 

The new trail will extend from the intersection at State Route 243 and Desert Aire Drive to the boat launch at the Columbia River. Along with the trail, traffic circles will be added at five intersections. 

Total project cost is about $340,000, with $294,100 coming from a federal grant. 

Traffic circles have the same purpose as — but are not - roundabouts, Bren said, which is to slow down traffic. The traffic circles in Desert Aire will be designed so that commercial trucks can drive over the edges.

A section of Stratford Road also is scheduled for repaving in 2025, from Road 20 NE to the crossing of the BNSF tracks, about 3 miles. That too is federally funded, and Bren said that project must be completed or the county will lose the money. 

County officials also will be working to upgrade Drumheller Road south of State Route 17, which would provide alternative north-south access from Mae Valley. The first phases will be grading sections of the road to make it easier to travel, Bren said, then graveling it. The work is projected to take several years, he said.

Cheryl Schweizer can be reached via email at [email protected].

ARTICLES BY CHERYL SCHWEIZER

Road projects on hold for Labor Day weekend
September 4, 2026 3:10 a.m.

Road projects on hold for Labor Day weekend

MOSES LAKE — With Labor Day weekend dead ahead, drivers will be able to move freely about the state. Most road projects are on hold for the holiday weekend. Nobody will be working on the Hansen Road overpass on Interstate 90, but the lane restrictions that are in effect will continue through the end of the project.

Cost estimates for water source alternatives given to Moses Lake City Council
September 3, 2026 3:50 a.m.

Cost estimates for water source alternatives given to Moses Lake City Council

Protected under the U.S. Endangered Species Act, efforts are ongoing to keep it self-sufficient

MOSES LAKE — It’s going to cost a lot of money to provide alternative water sources for the city of Moses Lake, but some of the possible alternatives will cost more than others. City officials provided the Moses Lake City Council with costs for various alternatives Tuesday.

Dryer vent cleaning is important -- but often overlooked
September 4, 2026 1:20 a.m.

Dryer vent cleaning is important -- but often overlooked

MOSES LAKE — Not all the maintenance a house needs is visible. Sometimes a potential problem just goes unnoticed until it causes trouble, sometimes serious trouble. But a lot of potential problems give off warning signs. Clothes dryers often do when they need a good cleaning.