Land use designation process for Moses Lake 12th elementary school still in the works
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 2 years, 8 months AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | March 21, 2024 1:20 AM
EPHRATA — Advertising for bids for — and construction of — the 12th elementary school in Moses Lake is on hold while the land sale is still pending. Grant County officials said the process of revising the land use designations to allow construction and use is ongoing.
The new school will be located at the intersection of Road N NE and Westshore Drive NE in Mae Valley. Architect Matt Whitish estimated at a March 2023 Moses Lake School Board meeting that the project could be advertised for bid by the end of 2023, with a groundbreaking in spring 2024.
Construction starting in spring 2024 would mean the building would be ready for occupancy about the start of the 2025-26 school year. But the project has not been advertised for bid yet, and site preparation and construction haven’t started.
Moses Lake Superintendent Monty Sabin said district officials are still deciding how they want to proceed when they do get permission to start the project.
“A firm decision hasn’t been made yet,” Sabin said.
The new school has not been named yet. Sabin said in an earlier interview that there’s a policy for that, and school officials will be working through the process.
Grant County Auditor Melissa McKnight said the assessor’s office does not yet have a survey recorded for the property. The Moses Lake School District is buying a section of a bigger piece of property the owners want to divide into additional parcels. That process requires what is called a short plat. A short plat needs a survey, which is the responsibility of the seller, and that hasn’t been submitted yet, McKnight said.
“We would love to move forward with it,” she said.
In the meantime the assessor’s office staff is working on the project where they can, she said. The property has been assigned a parcel number, but a recent computer system upgrade is causing problems in recording updated information.
“Every time we go to add a parcel number, we break (the system),” she said. “And it takes a day to unbreak it.”
The new school will be on 14 acres, which includes the building, the playfields and parking lots. The building will use the same basic design as Groff Elementary, with some modifications that came out of a couple of years of experience at Groff.
The parent pickup and drop-off areas will be bigger and the heating-cooling system will be modified. Access to the kitchen was changed to make it easier to deliver food. Classrooms on the second floor will be slightly bigger, and the windows will be slightly smaller.
Cheryl Schweizer can be reached via email at [email protected].
ARTICLES BY CHERYL SCHWEIZER
North Cascades Highway closed, possibly for the winter
WINTHROP — Snow slides along the North Cascades Highway closed the road early Thanksgiving evening, but Washington Department of Transportation officials aren't sure yet whether the road will be closed for the winter.
Water, sewer, parks improvements in Othello capital projects plan
OTHELLO — Upgrades to the heating-cooling system at Othello City Hall, a new shelter in Lions Park and upgrades to sections of 14th Avenue are among the possible projects for 2027 included in the city's six-year capital facilities plan.
Construction could mean temporary closure of South Pioneer Way intersection next spring
MOSES LAKE — A new roundabout is tentatively scheduled for construction at the intersection of Yonezawa Boulevard and South Pioneer Way in spring 2027.