Avista: Danger was minimal with dam mishap
CAROLYN BOSTICK | Hagadone News Network | UPDATED 1 year AGO
Carolyn Bostick has worked for the Coeur d’Alene Press since June 2023. She covers Shoshone County and Coeur d'Alene. Carolyn previously worked in Utica, New York at the Observer-Dispatch for almost seven years before briefly working at The Inquirer and Mirror in Nantucket, Massachusetts. Since she moved to the Pacific Northwest from upstate New York in 2021, she's performed with the Spokane Shakespeare Society for three summers. | November 2, 2024 1:00 AM
POST FALLS — Officials from the National Weather Service and Avista Utilities re-examined their emergency response procedures Wednesday, following a crane failure at the Post Falls Dam the day before.
The NWS issued a flash flood watch at 9:57 a.m. Tuesday after the crane toppled and struck the dam. This was the only alert sent to wireless devices near the waterway. The watch was canceled at 10:38 a.m. after dam operators gave the all-clear.
Charlotte Dewey, warning coordination meteorologist at the NWS, explained that Post Falls Dam is one of about 20 dams under their supervision.
"We work closely with the dam and operators to know what to do when or if this happens," Dewey said. "Our role is to alert the public and partners about some of the impacts from that potential dam failure to lives and communities downstream."
The dam, owned by Avista Utilities, maintains emergency action plans at all its hydroelectric facilities. These plans are regularly tested through training scenarios with emergency response partners like the NWS.
Dewey noted that had the situation worsened, the response would have escalated. "If it moves to an imminent failure, or it's confirmed that it's actually failing, then we can issue a flash flood warning, saying there's an imminent risk to life and property, and that flooding will actually happen within a short frame of time," she said.
Jared Webley, Avista's communications manager, explained why the emergency plan was activated despite the ultimately minor nature of the incident.
"The words 'potential failure' could be scarier than they actually may be, as indicated yesterday. We had a 15-minute timeframe where we didn't exactly know the extent of the damage," Webley said. "Out of an abundance of caution, they (the NWS) chose to send that out and that's spelled out in the emergency action plan."
Three additional dams downstream from Post Falls would have helped regulate water flow if a failure had occurred. The dam, in service since 1906, was undergoing multi-year construction upgrades when the crane incident occurred.
ARTICLES BY CAROLYN BOSTICK
Shoppers undeterred by Black Friday crowds in Coeur d'Alene
Although a long line formed outside the Bath and Bodyworks store at Silver Lake Mall, customers didn’t have to wait more than a few minutes before they got their turn to buy gifts for their loved ones at Black Friday prices.
Lake City Roofing spans three generations in North Idaho
Lake City Roofing spans three generations in North Idaho
Michael Farrar didn’t plan on getting into the family business, but when his job at an aluminum plant closed down, causing him to move away from North Idaho to stay with the company, he came home and got to work instead. Lake City Roofing first began in 1987 as a power washing company run by Michael’s parents, Myron and Lisa Farrar. Brothers Michael and Shaun Farrar officially took over the business since Jan. 1.
Deaths mourned at Coeur d'Alene Transgender Day of Remembrance ceremony
Deaths mourned at Coeur d'Alene Transgender Day of Remembrance ceremony
For more than a decade, Transgender Day of Remembrance has been marked in Coeur d’Alene by reading the names of those lost in the previous year.