Grant PUD budget reviewed at public hearing

CHERYL SCHWEIZER | Hagadone News Network | UPDATED 1 year, 5 months AGO
by CHERYL SCHWEIZER
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | October 10, 2024 2:25 AM

EPHRATA — After all expenses are paid the Grant County Public Utility District is projected to end 2025 at about $192.25 million in the black. The proposed 2025 budget was presented at two public hearings Tuesday. 

Expenses for 2025 are projected at $367.8 million; projected expenses for 2024 were about $347.2 million.  

Bryndon Ecklund, PUD lead financial analyst, said operations and maintenance expenses – the cost of doing business every day – are projected to increase about 12.6% when compared to the updated budget forecast for 2024. 

The demand for PUD services is projected to increase, but not as fast as anticipated earlier.  

“That’s the result of delayed construction as it relates to industrials,” Ecklund said. “The load we were expecting to see there is being delayed a little bit. Once we get out to 2026, 2027, that load forecast then increases over our prior load forecast.” 

Demand for PUD power is projected to grow by about 11.2% in 2025. 

The PUD is expected to make more money from its power sales, as the price it receives at auction increased in summer 2023 and has remained at higher levels in subsequent auctions, Ecklund said.  

Terrah Bicondova, manager of budget and reporting, said costs have gone up in most categories of operation. The utility hired additional people, raised salaries and benefits; labor costs are projected to increase by about 11%.  

Purchased services include consultants and other specialists and costs are budgeted to increase by about 25%. Operating materials and equipment costs are projected to increase by about 16%. General and administrative costs should increase by about 11.7%. 

“Costs that are in that category can be regulatory expenses, travel, training, miscellaneous operating expenses, things like that, Bicondova said.  

Insurance, technology and risk management costs also are budgeted to increase, she said. 

The PUD also has construction projects planned; Ecklund said spending on those, called capital projects, is projected to increase by about 47%, about $81 million. 

“We’re seeing a shift from our spending for capital being down at the dams to the electric system being a large driver of the capital spending,” he said.  

Spending on capital projects was projected at about $239.87 million. Utility district managers have identified 10 projects as priorities.  

“That’s essentially the projects that, if selected to fund them, that’s the total amount our project managers have said we could look to spend on (them) next year,” he said. “We have an all-day workshop (planned) to sit down with our portfolio working group, identify projects for funding and prioritize where we’re going apply that budget,” he said.  

Priority projects include the continuation of a multi-decade project to upgrade turbines and generators at Priest Rapids Dam, the start of planning and construction for a new maintenance facility, called a service center, in Ephrata and the planning for a new service center in Moses Lake. The list also includes work on a new transmission line between Wanapum Dam and the Quincy area, new transmission lines around Quincy and Royal City, and upgrades to the substation near Ruff. 

“We look at every single project that’s in the queue,” Ecklund said. “We work to prioritize projects in relation to continuing to meet our plan and goals.”

ARTICLES BY CHERYL SCHWEIZER

Road closures, roundabout, mean construction season underway
April 3, 2026 3 a.m.

Road closures, roundabout, mean construction season underway

EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”

Ybarra announces run for Washington Senate
April 2, 2026 1:48 p.m.

Ybarra announces run for Washington Senate

QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.

Othello Community Museum to open April 25
April 1, 2026 3:45 a.m.

Othello Community Museum to open April 25

OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.