Bid awarded for Ritzville fiber buildout
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 1 year, 7 months AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | September 4, 2024 3:00 AM
RITZVILLE — Installation of fiber optic cable within the Ritzville and Lind city limits will start sometime this fall and should be finished by spring 2025. Adams County Commissioners awarded a $2.97 million contract to Zero Db Communicatons of Spokane for the first phase of the broadband project.
Adams County Public Works Director Todd O’Brien said some areas of Ritzville already have access to fiber, but that the project will expand that access throughout town. The Lind portion will connect to an existing fiber line and build a fiber backbone around town.
The project is funded through a $10.3 million grant the county received from the Washington Department of Commerce in 2022. The goal, O’Brien said, is both to expand the network and provide high-speed service.
O’Brien estimated construction would begin by late September or early October. The contractor must accept the agreement, which then goes back to the commissioners for their approval. The contractor then has 10 days before the clock starts.
Work should continue throughout the winter, with completion projected in March or early April 2025.
“A lot of the work is hanging aerial (lines) on power poles,” O’Brien said, although some sections will be installed underground.
Due to long lead times for some items, county officials already purchased a lot of the necessary materials, O’Brien said.
Adams County Commissioner Dan Blankenship said that with the start of construction approaching, he’s been getting questions from constituents asking when it would be available.
“Soon,” Blankenship said.
The county is working on the buildout; actually providing internet to individual homes and businesses will be the work of private companies.
The second phase of the project is south of the Othello city limits, the area around the Othello Golf Club and some newer housing subdivisions. Any kind of construction requires permits and county officials are working on getting all the permits they need. That process has been underway for more than a year, O’Brien said.
County officials are working with three different utilities, and each company must evaluate its system and upgrade power poles where necessary. Permits also are required from the East Columbia Basin Irrigation District.
“My guess would be we will be able to bid (the second phase) contract sometime late this year, or most likely early next year,” O’Brien said.
If the permitting and contracting processes stay on schedule the second phase contract should be awarded about the time the first phase is finished, he said.
The two projects already underway will be funded with the existing grant, O’Brien said. Any further expansion would require another grant; O’Brien said the application process for a second grant opens later this year.
ARTICLES BY CHERYL SCHWEIZER
Road closures, roundabout, mean construction season underway
EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”
Ybarra announces run for Washington Senate
QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.
Othello Community Museum to open April 25
OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.