Money allocated for irrigation project north of I-90
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 1 year, 4 months AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | April 30, 2025 3:25 AM
MOSES LAKE — About $44 million in state funding will be allocated to a section of the Odessa Groundwater Replacement Project as part of the Washington Senate’s capital budget. The budget was approved Sunday.
The allocation comes with the proviso that it be spent on one section of the project, EL 22.1. The OGWRP project is designed to convert farms that use groundwater for irrigation to surface water.
Most of the property that would be affected is considered to be part of the Odessa aquifer. The land that would be served by the new canal is east of Moses Lake and north of Warden in Grant and Adams counties.
The irrigation water would be provided by the East Columbia Irrigation District, and Jon Erickson, ECBID development coordinator, said there are still some questions to be answered about how the irrigation district will and can proceed.
“We don’t have a clear direction on how to move forward,” Erickson said.
The allocation and the stipulations around it will be reviewed by the ECBID directors, beginning with their May 7 meeting, Erickson said.
The EL 22.1 Landowners Association, which was involved in obtaining the funding, said the project is fully designed.
“Construction would begin early next year, and the timing depends somewhat on when the public funding is made available,” said an EL 22.1 spokesperson in response to an email from the Columbia Basin Herald.
The project will receive about $40 million in matching funds from area farmers, according to a press release from Ninth District Senator Mark Schoesler, R-Ritzville. Schoesler said he worked with 13th District Sen. Judy Warnick, R-Moses Lake.
“With this capital budget funding and the matching money from growers, this project is ready to start,” Warnick said.
“(The landowner group) is in the process of obtaining the matching funding and with the public funding now allocated, the private matching funding should happen in 2026,” the spokesperson said. “(The private funding) could be used in later phases as the legislature included in the budget proviso that the EL 22.1 Project could be done in phases.”
The project would be the first in the groundwater replacement area north of Interstate 90, according to the landowner group. Some sections of the project south of I-90 can’t have water delivered due to the need to widen the canal, which will require widening some bridges along the canal’s course. Planning and design are underway on the first bridge, with construction scheduled to begin in October after the end of the irrigation season.
The canal and bridges north of I-90 were widened about half a century ago, the EL 22.1 spokesman said, so there’s capacity for additional water delivery.
“Consequently, work on EL 22.1 can begin as surface water delivery is assured,” the spokesman said.
ARTICLES BY CHERYL SCHWEIZER
Road projects on hold for Labor Day weekend
MOSES LAKE — With Labor Day weekend dead ahead, drivers will be able to move freely about the state. Most road projects are on hold for the holiday weekend. Nobody will be working on the Hansen Road overpass on Interstate 90, but the lane restrictions that are in effect will continue through the end of the project.
Cost estimates for water source alternatives given to Moses Lake City Council
Protected under the U.S. Endangered Species Act, efforts are ongoing to keep it self-sufficient
MOSES LAKE — It’s going to cost a lot of money to provide alternative water sources for the city of Moses Lake, but some of the possible alternatives will cost more than others. City officials provided the Moses Lake City Council with costs for various alternatives Tuesday.
Dryer vent cleaning is important -- but often overlooked
MOSES LAKE — Not all the maintenance a house needs is visible. Sometimes a potential problem just goes unnoticed until it causes trouble, sometimes serious trouble. But a lot of potential problems give off warning signs. Clothes dryers often do when they need a good cleaning.