Grant PUD budgets for projects in 2026
CHERYL SCHWEIZER | Hagadone News Network | UPDATED 7 months, 2 weeks AGO
Senior Reporter Cheryl Schweizer is a journalist with more than 30 years of experience serving small communities in the Pacific Northwest. She began her post-high-school education at Treasure Valley Community College and enerned her journalism degree at Oregon State University. After working for multiple publications, she has settled down at the Columbia Basin Herald and has been a staple of the newsroom for more than a decade. Schweizer’s dedication to her communities and profession has earned her the nickname “The Baroness of Bylines.” She covers a variety of beats including health, business and various municipalities. | August 19, 2025 3:00 AM
EPHRATA — Grant County Public Utility District customers will have through Dec. 9 to submit their comments on the 2026 PUD budget. The PUD’s preliminary budget projects about $236.9 million in hand at the end of the 2026, but Public Information Officer Christine Pratt said the final budget could, and will, look different.
“Department budgets are still being written, so those numbers are sure to change,” Pratt said in answer to an emailed question from the Columbia Basin Herald.
The preliminary budget includes a 2% rate increase, but that can be changed by the commissioners, Pratt said. The 2025 budget included a 3% increase.
The preliminary total budgeted expenses were projected at about $434 million, which includes both planned expenditures with some anticipated revenues subtracted.
Utility district officials always have a long list of projects, and 2026 is no exception. The most expensive are ongoing projects, among them expanding access to electrical power in the Quincy area, a new maintenance facility in Ephrata, upgrades to the turbines and generators at Priest Rapids Dam and reinforcing the spillways at Priest Rapids.
The Quincy transmission lines will connect Quincy directly with Wanapum Dam. The preliminary estimate of the work for 2026 was about $97.3 million.
That will include work on the new transmission lines — which have prompted concern from some property owners along the route — additional substations, and more connections between existing and new substations.
The new maintenance center will be on property purchased by the PUD from Grant County, near the site of the new Grant County Jail. It’s the first phase of a project that will eventually include a new headquarters. The first phase is projected to cost about $87 million.
The turbine-generator upgrades are part of a multi-decade project to upgrade the turbines and generators at both Priest Rapids and Wanapum. The Wanapum phase is complete, and crews are more than halfway through the work at Priest Rapids. Completion is projected for 2030.
The project includes disassembling turbines and generators, replacing parts that have worn out, and revising the design of the turbines to improve fish survival and increase efficiency. The projected cost for 2026 is about $44.5 million.
The spillway upgrades followed the discovery of a leaking joint on a spillway pillar in 2017. Further analysis prompted PUD officials to add support to all the pillars across the dam. Total cost for 2026 is projected at $31 million.
The public can submit comments on the budget through Dec. 9 at grantpud.org.
ARTICLES BY CHERYL SCHWEIZER
Road closures, roundabout, mean construction season underway
EPHRATA — The grass is starting to turn green, the trees are starting to leaf out, construction crews are starting to build roundabouts – hey, it’s spring. At least one roundabout project is in its final phase, held over from fall 2025. The intersection of State Route 282 and Nat Washington Way will be closed the week of April 6 to allow crews to install permanent lights. “This really is the final (closure),” wrote Grant County Administrator Tom Gaines in a media release. “The roundabout will close at 6 a.m. Monday, and we plan to reopen by Friday, possibly sooner if the work finishes early.”
Ybarra announces run for Washington Senate
QUINCY — State Representative Alex Ybarra, R-Quincy, has announced his candidacy for the Washington Senate. If he’s elected, he would replace Judy Warnick, R-Moses Lake, who announced her retirement in March.
Othello Community Museum to open April 25
OTHELLO — With a couple of new exhibits, a new heating-cooling system, rearranged displays and a thorough cleaning, the Othello Community Museum will open for the summer April 25. The goal, said Molly Popchock, museum board secretary, is to operate for a full season.